Challenge

Project 2_Design & Analysis of a Hostel building at Guwahati, Assam

Q1. ) In this project, participants will get to experience the entire design process from modelling, analysis, design, and preparation of construction drawings. The architectural drawings of a G+3 RCC building is provided. The following information on the building is to be used:

  • Location – Guwahati, Assam
  • Function – Hostel block in an academic institute

The walls will be made of AAC blocks. Other loadings are to be calculated as per the architectural drawings.

The buildings rests on type 3 soil. Piles of length 10 meters and 500 mm diameter with a load-carrying capacity of 280 KN is to be used.

The ground floor level will be at a height of 2 meters above the existing site level to avoid floodwater enter the building.

M25 grade of concrete with Fe500 for longitudinal reinforcement and Fe 415 for shear reinforcement is to be used.

The following design IS codes will be required for reference:

  • IS 875 part 1
  • IS 875 part 2
  • IS 13920
  • IS 1893
  • IS 2911 part 2
  • IS 456
  • SP 34

Students will have to produce the following:

  • Etabs model for the two blocks on either side of the expansion gap
  • Foundation details illustrating the pile & pile cap reinforcement
  • Tie beam details connecting the pile caps
  • Column reinforcement
  • Framing plan for typical floor
  • Beam reinforcements for ground floor

AIM :- The structural model needs to be created and analysed using the specified building in ETABS 2018 in line with IS 1893 and IS 13920. To design the specifics for the pile cap and pile reinforcement, To create the ground floor frame plan, the column reinforcements, the tie beam linking the pile caps, and the ground floor beam detailing.

provided data:

AAC blocks are used to build the wall. Pile strength: 280 kN, M25 steel, Fe 500, and soil type 3.

INTRODUCTIONS:-

  • Etabs is the name of the program that creates a structural model of a particular structure.
  • The grid spacing values from the included structural designs should be noted first.
  • After building the structural model, run it next.
  • Take notes on the ETABS result numbers after you analyze the results.
  • The SAFE 2016 software is then used to design the foundations using the model.

PROCEDURE:-

  • Open the Etab software, then select File > File > New Model from the menu.
  • A window for initializing the model will appear.
  • Select the Indian codes by clicking the use built-in setting, then click "OK."
  • Select the custom grid data, then select OK.
  • As soon as the values specified in the plans are inserted, our model will be complete.
  • The next step is to define the material. Go to define, select material properties, and then specify the concrete and rebar materials.
  • Properties need to be defined in the subsequent step section. Add the beam and column specification by going to define and clicking on section properties.
  • 450 mm x 600 mm beam size is provided for the all the beams.
  • 450 mm x 600 mm beams are provided for the beams at periphery so as to increase the torsional resistance of the building
  • Moment of inertia for beams and columns should be reduced by 0.35% and 0.4% respectively.
  • In the next step define the slab properties by going in to define and slab sections. Add the slab property as While defining the slab for Stair case it should be One way .
  • Describe the stair case slab and specify that it is 175 mm thick (ranges from 175-225 mm).
  • Using the beam command, draw every beam.
  • Use the column command to draw every column.
  • The slabs command is used to draw slabs in the subsequent step.
  • We now need to decide where the shear walls will be placed and how long they should be.
  • According to Indian standards, the wall's length should be 5-2% in each direction.
  • It is assumed that the shear wall is 250 mm thick.
  • Go ahead and define the loads now.
  • The loads are then added after choosing the beams and floors.
  • AAC load of 3.5 kN/m since the aac blocks are used.
  • The live loads values are got from Is 1875 part 2 for residential buildings.
  • As per table 1 of IS 875 part 2
  • For hostel buildings

Living Rooms,Bedrooms and dormitories

2 kN/m^2

Kitchen and Laundries

3 kN/m^2

Billiards and public lounges

3 kN/m^2

Store rooms

5 kN/m^2

Dining rooms,cafeterias and restaurant

4 kN/m^2

Office rooms

2.5 kN/m^2

Bath and toilets

2 kN/m^2

Corridors, passages, staircase

3 kN/m^2

Balconies

4 kN/m^2

  1. As per clause number is 875 part2 reduction factor should be applied on the imposed loads.
  2. Live load at the roof floor needs to be reduced hence 2 kN/m is applied.
  3. Floor finish on all the floors 2 kN/m is applied.
  4. Seismic loads should be define so as per IS 1893 Table no. 8 importance factor should be 1.2
  5. Since the building.
  6. Time period is calculated as per clause number 7.6.2 of IS 1893

T=0.09h/sqrtd

Tx=(0.09*16.85)/(67.7)^0.5=0.184 Seconds. Or Ty=0.09*16.85/(13.3)^0.5=0.415 sec

  1. Now define the load combinations
  2. In the next step we have to define the mass source, for that go to define and click on mass source and add on the new , click on specified load data , in the mass options click on include lateral mass and lump lateral mass at story levels,in the load pattern add multiplier 0.25 for LL and 1 for all the dead and super dead loads.
  3. And select all the floors and apply diaphragm D1
  4. In the next step we have to define for the modal cases for that go to define and click on modal cases click add new model cases select eigen and put the number of modes shape required.
  5. now go to define function and click on response spectrum and add anew function in accordance with IS 1893-2016 check all the values click ok.
  6. Name the function as IS function,Response spectrum IS function IS 1893-2016 tab will appear check all the values Seismic zone factor soil type,importance factor click on linear x linear y click ok.
  7. now go to define Load cases and click on Add new case and Add RSX and Rsy
  8. select the response spectrum click on Add select the function as IS function and U1 for Rx, and U 2 for Rsy and IS function
  9. Go to define click on load combinations and click on default design combo,click on create frame design and click on convert to design combo click ok.
  10. Now check the model if there are any warning correct it and run the model.

Results and discussion

  1. Go to display then click show tables and then structural data click ok.
  2. Click on show tables , select the Analysis results structure output click ok.
  3. Select the base reaction and check the eqx eqy vales , Rx and Ry value see which values are larger if the rX RY values are lesser than the Eqx Eqy unlock the model and then go to define load case and delete the Rx RY cases and again select the load combinations and define that again.
  4. Go to modal mass participation ration and check the values for U1 U2 U3 values sume of these UX Uy UZ for the first 3 modes it should be greater than 65%.
  5. Go to concrete frame design and select the start design or check . and note down the va;ues of reinforcement details.

2.select modal participating ratios we have got that at mode 7 we have got above 90% so its ok.

3.now select the base reactions check that Eqx Eqy values should be same and Rsx and Rsy values also should be atleast equal to Eqx and Eqy respectively. if not then just take the rsx values and divide it by Eq values whatever the values will get that values needs to be multiplied in the load cases rsx tab.

  1. Hell for the proportion of jarring walls visit the base level, then select reaction When ex and ey values are available, divide them by two. A minimum of 90% should be the total base shear. Add the shear walls now in the proper directions.

.

Beam 14 Right end Centre Left End
Bottom Reinforcement 672 605 609
required
Dia of bars 20 20 20
Number of bars 2.140127389 1.926751592 1.939490446
Bottom Reinforcement 675 605 605
Provided at Top 2.149681529 1.926751592 1.926751592
1#24 +2#24 extra is provide 2#20 is provide 2#20 is provide
COLUMN DESIGN
COLUMNS ALONG THE GRID 1B Column dimension 450*600
1 Longitudinal Reinforcment calculation
a) Minimum Reinforcment 0.8% of Gross cross sectional Area 2160 mm^2
As per clause no.26.5.3.1 of Is 456 2000
b) Maximum Reinforcment 6% of Gross cross sectional Area 15600 mm^2
As per clause no.26.5.3.1 of Is 456 2000
c) Maximum Ast along 3 A 4739 mm^2
As per clause no.26.5.3.1 of Is 456 2000
Dia of the longitudinal Reinforcment should 12 mm or more
There for using 16 mm dia bars
Dia of bar 24
Area of 1 bar 452.448
number of bars 10.47413183
There fore using 8 number of 28 mm dia bars Ast 4524.48 mm^2
remaining St Ast 214.52 mm^2
2 number #12 extra longtidudinal Reinforcements needs to be provided Ast 628 mm^2
There fore total longitudinal reinforcment provided
10 no. of 24 mm dia bars 4525
2no. Of 12 mm dia bars 628
Ast provided 5152.48 mm^2
The spacing between the longitudinal bars should not exceed 300mm.
2 Shear Reinforcment calculation
a) Minimum dia for shear Reinforcment for 32 mm dia 8 mm
As per clause no 7.4.2 of IS 13290- 2016
b) Maximum Shear reinforcment from the Etabs out put 665 mm^2
c) There for using 8 mm dia bars mm^2
Dia of bar 8
Area of 1 bar 50.272
Special confining reinforcement clause no 8 of IS 13290 2016
The special cofining reinforcement shall be provided at lo.
lo should not be less tham
larger lateral dimension of the column 600
1/6 of the clear span of member 554.1666667
450 mm 450
There fore lo = 600 mm
The spacing of shear reinforcment along lo should not be more than
a 1/4 of minimum dimension of beam/column
minimum dimension of column 150 mm
1/4th of minimum dimension of column 112.5 mm
b 6 times the dia of smallest longitudinal reinforcement bar
Dia of smallest longitudinal reinforcement bar 12 mm
6 times the dia of smallest longitudinal reinforcement bar 72 mm
c 100 mm 100 mm
There fore for special confining reinfrocemnet #8mm @100 mm c/cis provided in the lo zone.
Transverses Reinforcment calculation for the zone upto h/4.
hc in m Beam depth h
Height of the column of Plinth level column 1 0.6 0.4
Height of the column ofGF column 3.45 0.6 2.85
Height of the column of FF column 3.45 0.6 2.85
Height of the column of SF column 3.45 0.6 2.85
Height of the column of TF column 3.45 0.6 2.85
h h/4 approximate
Plinth level 0.4 0.1 200 mm
GF 2.85 0.7125 800 mm
FF 2.85 0.7125 800 mm
SF 2.85 0.7125 800 mm
TF 2.85 0.7125 800 mm
Transverse reinforcement in the splice Zone as per clause number 7.4.of IS 13290 2016
As per the clause nuo. 7.4.1 of IS 13290 2016 the ends should have 135 hook with an
extension of 6d of bars.
d 32 mm
6d 192 mm
As per the clause nuo. 7.4.2 of IS 13290 2016
a 8 mm dia bars are used in stirrups if the dia of longitudinal bars is less than or equal to 32 mm
b The maximum c/c spacing of stirrups is 300 mm
c a cross tie should be provided if the dimension of the column exceeds 300 mm.
There fore upto h/4 #8mm @300 mm c/cis provided in the lo zone.
As per the clause no. 7.3.2.1 of IS 13290 2016
100 mm spacng should be provided within this splicing zone
There fore in the splice zone #8mm @100 mm c/cis provided in the lo zone.
For the columns terminating in the footing
as per clause nummber 8.2 of IS 13290 2016.
special confinement reinforcement should be provided upto 300 mm or larger length inside the footing.
COLUMNS ALONG THE GRID 3B Column dimension 450*650
1 Longitudinal Reinforcment calculation
a) Minimum Reinforcment 0.8% of Gross cross sectional Area 2340 mm^2
As per clause no.26.5.3.1 of Is 456 2000
b) Maximum Reinforcment 6% of Gross cross sectional Area 17550 mm^2
As per clause no.26.5.3.1 of Is 456 2000
c) Maximum Ast along 3 A 5022 mm^2
As per clause no.26.5.3.1 of Is 456 2000
Dia of the longitudinal Reinforcment should 12 mm or more
There for using 16 mm dia bars
Dia of bar 28
Area of 1 bar 615.832
number of bars 8.154821445
There fore using 8 number of 32 mm dia bars Ast 4926.656
Remaning Ast Ast 95.344
There for using 16 mm dia bars
Dia of bar 16
Area of 1 bar 201.088
number of bars 0.474140675
There fore using 2 number of 20 mm dia bars Ast 402.176
There fore total longitudinal reinforcment provided
8 no. of 28 mm dia bars
2no. Of 16 mm dia bars
Ast provided 5328.832 mm^2
The spacing between the longitudinal bars should not exceed 300mm.
2 Shear Reinforcment calculation
a) Minimum dia for shear Reinforcment for 32 mm dia 8 mm
As per clause no 7.4.2 of IS 13290- 2016
b) Maximum Shear reinforcment from the Etabs out put 720.48 mm^2
c) There for using 8 mm dia bars mm^2
Dia of bar 8
Area of 1 bar 50.272
Special confining reinforcement clause no 8 of IS 13290 2016
The special cofining reinforcement shall be provided at lo.
lo should not be less tham
larger lateral dimension of the column 650mm
1/6 of the clear span of member 554.1666667
450 mm 450
There fore lo = 650 mm
The spacing of shear reinforcment along lo should not be more than
a 1/4 of minimum dimension of beam/column
minimum dimension of column 450 mm
1/4th of minimum dimension of column 112.5 mm
b 6 times the dia of smallest longitudinal reinforcement bar
Dia of smallest longitudinal reinforcement bar 20 mm
6 times the dia of smallest longitudinal reinforcement bar 120 mm
c 100 mm 100 mm
There fore for special confining reinfrocemnet #8mm @100 mm c/cis provided in the lo zone.
Transverses Reinforcment calculation for the zone upto h/4.
hc in m Beam depth h
Height of the column of Plinth level column 1.5 0.5 1
Height of the column ofGF column 4 0.5 3.5
Height of the column of FF column 3.45 0.5 2.95
Height of the column of SF column 3.45 0.5 2.95
Height of the column of TF column 3.45 0.5 2.95
3.45 0.5 2.95
h h/4 approximate
Plinth level 1 0.25 300 mm
GF 3.5 0.875 900 mm
FF 2.95 0.7375 900 mm
SF 2.95 0.7375 900 mm
TF 2.95 0.7375 900 mm
Transverse reinforcement in the splice Zone as per clause number 7.4.of IS 13290 2016
As per the clause nuo. 7.4.1 of IS 13290 2016 the ends should have 135 hook with an
extension of 6d of bars.
d 32 mm
6d 192 mm
As per the clause nuo. 7.4.2 of IS 13290 2016
a 8 mm dia bars are used in stirrups if the dia of longitudinal bars is less than or equal to 32 mm
b The maximum c/c spacing of stirrups is 300 mm
c a cross tie should be provided if the dimension of the column exceeds 300 mm.
There fore upto h/4 #8mm @300 mm c/cis provided in the lo zone.
As per the clause no. 7.3.2.1 of IS 13290 2016
100 mm spacng should be provided within this splicing zone
There fore in the splice zone #8mm @100 mm c/cis provided in the lo zone.
For the columns terminating in the footing
as per clause nummber 8.2 of IS 13290 2016.
special confinement reinforcement should be provided upto 300 mm or larger length inside the footing.

Importing the software Safe 2016

  1. Go to file click on export and select the safe v12.fk.
  2. A tab will appear then click on the story as base and select the loads and loads from above click on the combination click ok,
  3. Goto SAFE 2016 and go to file click import and select the file and save the file as FDB.
  4. Go to dispay click on the show loads select dead above and love above the values will be appeared.

Given data:-

Column of size:- 450mm *600 mm & 600mm*450m m

pile has a load carrying capacity of 280kN

Pile length-16 m and dia of pile -500 mm

SBC-150kN/m^2

Solution:

  1. Number of piles=Total Axial load/pile capacity=(1.5DL+1.5LL)/280= numbers
  2. Piles in the springs are defined as spring so for that the spring constant

K=EA/L

E=5000(fck)^0.5=5000(25)^0.5=25000 N/mm^2

Area of pile =22/7*d^2=3.142*(500)^2/4=196375m^2

L-10000m

K=25000*0.7855/16=306835.9N/mm==419.

  1. Spacing of the piles as per clause number 6.6.2 of IS 2911 the spacing between the piles =2.5dia of the piles =2.5*500=1250mm
  1. Now in the next step we have to define the material properties for go to define and define the material properties of Concrete and Reinforcement properties Fe500 & Fe 415.
  2. Select the values .
  3. Go to define section properties and define pile caps ,pile Dia , and column
  4. Add new , defined pile cap pile 500 as Mat , and Column as Stiff.
  5. Click on the quick draw around the plots a window will open there insert the columns sizes and these columns to their specified positions. Columns should be stated as stiff material.
  6. In the next step pile caps needs to be drawn for that go to Quick draw slab command select pile caps and add it. Piles and pile cap should be stated as stiff material.
  7. Select the pile caps and changed the rebar material as Fe 500 .
  8. Next go to draw and draw point and a window will open up there draw the points where piles are to be drawn.
  9. Now again select the quick dfaw around the pints there select the property circular slab add piles dia in this case 0.5m and add to the points. Select these piles and again check for the rebar materials.
  10. Now we have to define all the piles as spring for that go to define
  11. select soil spring properties add new property there click on compression only and add the calculation value of K=EA?L.
  12. Select all the piles and go to assign and select support data and select spring properties and assign it.
  13. Go to define and select the define beam and define the tie beams whose thickness should be as of pile caps.
  14. Check weather the rebar material is Fe 500 under design preferences
  15. Go to define and define the load combinations sls and uls
  16. Go to design and design preferences
  17. Save the model and run the Analysis
  18. Deformed shapes showed that deformations are negligible
  19. Assign add the design strips
  20. Run the analysis
  21. Deformed shape all the values are less than 25 mm hence ok.
  22. Now go to display and click on the punching shear the values we have go are less than 1 hence ok.
  23. Now go to display and select slab design.
  24. All the reinforcement details will be available
  25. For X DIRECTION MIDDLE STRIP

maximum Reinforcement was

For Top:- 29834 mm^2/m=29834/3.3=9041 mm^2=28 nos. 20 mm dia are provided

For Bottom-13326mm^2/m=4038 mm^2=13 nos. 20 mm dia are provided

  1. For layer Y direction

maximum Reinforcement was

For Top:- 19926= 3831mm^2/m=12 nos of 20 mm dia are provided

For Bottom-22784mm^2/m=4398 mm^2=14 nos 20 mm dia are provided

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.