Challenge

Preparing Schedule & Cost Estimation for a building using REVIT

1) Use the shortcut keys in Revit discussed in class to complete the following tasks and list them below
a. Using 3D model create a section box
b. To create similar doors and windows in a floor plan layout
c. To reduce the thickness of lines visible in plan views
d. To apply override settings to a floor in the model section view
e. To increase the range of visibility in a plan view
f. To select the previously selected items
g. To add annotations to the model views
h. To bring the model elements in line
i. To rotate the model elements
j. To move an object to another location
k. To copy a model element
L. To mirror an element about an axis
m. To create an array of model elements

A) The shortcut keys for the given tasks are listed below.

2) Using Revit and the project used from week 6 to 8 prepare a schedule for the following
a. Walls
b. Doors
c. Windows
d. Material-Concrete/Wood

AIM: To prepare a schedule for the given elements using revit

INTRODUCTION:
A schedule is a tabular display of information, extracted from the properties of the elements in a project. A schedule can list every instance of the type of element you are scheduling, or it can collapse multiple instances onto a single row, based on the schedule's grouping criteria.
You can create a schedule at any point in the design process As you make changes to the model that affect the schedule, it automatically updates to reflect those changes. You can add a schedule to a drawing sheet
You can export a schedule to another software program, such as a spreadsheet program

PROCEDURE

Step: 1
First we have to open the revit project and go to the view tab and select the schedules option
After selecting the schedules option the new tab will appears as shown below
Next we need to select the wall schedule and press ok as shown below.
Next the schedule properties tab will be displayed, as shown below Next we need to select the scheduled fields in order and click ok
Next the wall schedule tab will be displayed, as shown in the below figure.

Step: 2
First we have to open the revit project and go to the view tab and select the schedules option.
After selecting the schedules option the new tab will appears, as shown below.
Next we need to select the door schedule and press ok, as shown below.
Next the schedule properties tab will be displayed, as shown below.
Next we need to select the scheduled fields in order and click ok.
Next the door schedule tab will be displayed, as shown in the below figure.

Step:-3
First we have to open the revit project and go to the view tab and select the schedules option.
After selecting the schedules option the new tab will appears, as shown below. .
Next we need to select the window schedule and press ok, as shown below
Next the schedule properties tab will be displayed, as shown below.
Next we need to select the scheduled fields in order and click ok.
Next the window schedule tab will be displayed, as shown in the below figure

Step: 4
First we have to open the revit project and go to the view tab and select the Material takeoff option.
After selecting the Material takeoff option the new tab will appears, as shown below.
Next we need to select the wall material and press ok, as shown below.
Next the Material takeoff properties tab will be displayed, as shown below. .
Next we need to select the scheduled fields in order and click ok
Next the Wall Material takeoff tab will be displayed, as shown in the below figure.

RESULT:
Prepared a schedule successfully for the given elements using revit.

3) Using Revit Calculate area and volume of each room in the model with appropriate room tags applied to each room. Prepare a schedule report for area and volume of each room.

AIM: To prepare a schedule report for area and volume of each room in the model.

INTRODUCTION:
A schedule is a tabular display of information, extracted from the properties of the elements in a project.
A schedule can list every instance of the type of element you are scheduling, or it can collapse multiple instances onto a single row, based on the schedule's grouping criteria.
You can create a schedule at any point in the design process.
As you make changes to the model that affect the schedule, it automatically updates to reflect those changes. You can add a schedule to a drawing sheet
You can export a schedule to another software program, such as a spreadsheet program.

PROCEDURE

Step: 1
First we have to open the revit project and go to the view tab and select the schedules aption After selecting the schedules option the new tab will appears as shown below.
Next we need to select the Room schedule and press ok, as shown below

Step:-2
Next the schedule properties tab will be displayed, as shown below.
Next we need to select the scheduled fields in order and click ok.

Step: 3
Next the Room schedule tab will be displayed, as shown in the below figure.

RESULT:
Prepared a schedule report successfully for area and volume of each room in the model.

4) Using the same schedule using the unit cost rate for materials available in the internet, prepare total cost of materials used in the project
a. Total Cost of Materials
b. Individual Material Take off

AIM:- To prepare total cost of materials using the unit cost rate for materials available in the internet.

INTRODUCTION:
Material takeoff schedules list the sub-components or materials of any Revit family.
Material takeoff schedules have all the functionality and characteristics of other schedule views, but they allow you to show more detail about the assembly of a component.
Any material that is placed in a component within Revit can be scheduled.

PROCEDURE

Step:-1
First we have to open the revit project and go to the view tab and select the Material takeoff option.
After selecting the Material takeoff option the new tab will appears.
Next we need to select the door material and press ok..
Next the Material takeoff properties tab will be displayed.
Next we need to select the scheduled fields in order and click ok.
Next the Door Material tab will be displayed, as shown in the below figure.

Step: 2
First we have to open the revit project and go to the view tab and select the Material takeoff option.
After selecting the Material takeoff option the new tab will appears.
Next we need to select the Wall material and press ok.
Next the Material takeoff properties tab will be displayed.
Next we need to select the scheduled fields in order and click ok.
Next the Wall Material tab will be displayed, as shown in the below figure.

Step:-3
First we have to open the revit project and go to the view tab and select the Material takeoff option.
After selecting the Material takeoff option the new tab will appears.
Next we need to select the Window material takeoff and press ok..
Next the Material takeoff properties tab will be displayed.
Next we need to select the scheduled fields in order and click ok.
Next the Window Material takeoff tab will be displayed, as shown in the below figure.

Step:-4
First we have to open the revit project and go to the view tab and select the Material takeoff option.
After selecting the Material takeoff option the new tab will appears.
Next we need to select the Floor material and press ok..
Next the Material takeoff properties tab will be displayed.
Next we need to select the scheduled fields in order and click ok.
Next the Floor Material takeoff tab will be displayed, as shown in the below figure.

Step:-5
First we have to open the revit project and go to the view tab and select the Material takeoff option.
After selecting the Material takeoff option the new tab will appears.
Next we need to select the Furniture material and press ok.
Next the Material takeoff properties tab will be displayed.
Next we need to select the scheduled fields in order and click ok.
Next the Furniture Material takeoff tab will be displayed, as shown in the below figure.

RESULT:
The total cost of materials has been prepared successfully using the unit cost rate for materials available in the internet.

5) Using the concept of Visual Programming discussed in class, list a flowchart for the following scenario
a. How to decide framings for a structure using Dynamo ?
b. If there is no water coming from the pipes.
c. If request for money from client has been declined for the project.

AIM:- To list a flowchart for the given scenarie
a) How to decide framings for a structure using Dynamo?
b) if there is no water coming from the pipes.
c) if frequest for money from client has been declined for the project

PROCEDURE

Step:-1
a)How to decide framings for a structure using Dynamo ?

Step:-2
b) If there is no water coming from the pipes.

Step:-3
c) If request for money from client has been declined for the project.

RESULT:
The flowcharts are successfully listed for the given scenario.

6) List the parameters associated with each model element
a. Wall
b. Floor
c. Door
d. Window
e. Table
f. Building

A) Parameters associated with each model element are listed below:

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.