Challenge

Identification of Cracks

1.(a) observation:

concrete crushed and the reinforcement is exposed

concrete spalled beyond the reinforcement which may be a sign of rupture

beam top portion looks safe because of the flange advantage from slab

the crack develops from bottom to top means rebar yeilding occurs in support bottom only.

its form of flexural failure due to reversal of stress during earthquake

during stress reversal , support top experiences compression and bottom experiences tension

top compression is managed by slab advantage. bottom was not satisfied by the provided reinforcement

since the reinforcement got yeilded , it can not be repaired.

1.(b) observation:

cracks along beam -column edge

cracks seem to have developed through the structure as it looks much wider

beam looks separated from the column at the joints

concrete is not severely crushed

its beam pull out failure due to insufficient development length of reinforcement in joints.

during earthquake , the horizontal movement of structure makes this condition worse and detached the beam member from column

providing anchorage length between two existing concrete is very difficult. so not repairable.

1.(c) obsetrvation:

cracks are exactly at the joint of column - beam

cracks in beam developed through its entire width

slab also developed more cracks along the beam width direction

its a platis hinge failure

the damage occured only in the joint zone first of all

cyclic lateral loading and stress reversal at the joints led to the damage

even slab participated to its best to handle the tension (slab is severely cracked means it has undergone tension with its flange condition ) but unable to control damage

the joint can be strengthened

2.(a) observation:

concrete damaged at the top of a column

concrete damaged all around the column face

beams are safe

location of column looks at the edge of the building

no walls are built along the column, means it is probably at the ground floor , for parking car movement access

its a soft storey failure. technically plastic hinge formatioin

due to absence of infill walls at the ground floor, the plastic hinge forms at the top of ground storey columns during lateral movement

based obn the development of crush of concrete , it can either be repairable or not

2.(b) observation:

concrete developed complete breakage diagonally

longitudinal reinforcements are intact

shear reinforcement spacing looks wider( probably lesser shear rebar provided)

its pure shear failure

inadequate shear reinforcements compels concrete takes all the shear stress

2.(c) observation:

column failed completely

failure at top of column

there are two slabs connected to the column , probably one at mid height of the column

the wooden piles might be post failure support after column failed , providing temporary prop to avoid collapse of the entire structure

its a short column failure

an additional or beam connected to a column in mid height leads to its effect

this leads to failure especially if the connection is uni tentional and not accounted in design

the failure given in the picture is not at all repairable

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.