Commercial and Industrial Structures and Project Execution Stages
A free lesson from Skill-Lync's Basic Structural Engineering Concepts of Industrial Structures course, on Grow by Skill-Lync · Last updated 16 Nov 2026 · Session: “Introduction to Commercial and Industrial Structures”
What will you learn in this free Basic Structural Engineering Concepts of Industrial Structures lesson?
The lesson describes commercial buildings and industrial structures such as pipe racks and technological structures that support equipment, piping and cable trays. It then walks through the three project stages, proposal, basic engineering (FEED) and detailed engineering, and the documents each produces, including PFDs, P and IDs, plot plan and material takeoff.
- Types of commercial buildings
- What industrial structures support in a plant
- Proposal, basic and detailed engineering stages
- Basic engineering package documents
What comes after lesson 2?
The next free lesson is lesson 3, “Roles of Engineering Disciplines in Industrial Projects” (20 min). Later in Skill-Lync's Basic Structural Engineering Concepts of Industrial Structures course (paid): lesson 4, Civil Department in Engineering Projects; lesson 5, Structural Engineering in Industrial Projects Recap; lesson 6, Loads on Industrial Structures. The full course has 12 lessons (4 h 4 min of video); see the course overview or its price and syllabus.
Lesson transcript
Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.
Commercial structures. Commercial structures are building designed for retail, small-scale, and wholesale trading. So, commercial building generally are buildings used by businesses to sell their produce to the consumers. Also, in other words, we can say commercial buildings are building where commercial activities takes place. Commercial building includes office building, retail spaces, warehouses, and many more. Sometimes, the commercial building may be combined with the residential space. There are many examples of commercial buildings. The most popular ones are office buildings. Office buildings are categorized into various size and quality, like low-rise building, a mid-rise building, or a high-rise building. Also, an office by its quality may be rated as a 5-star building, or a 3-star building, or a general occupancy.
Another type of commercial building. Another type of commercial building is a retail building. Another type of very common commercial building is a retail building. A retail building may be a freestanding building, or a non-freestanding building. There are many examples of commercial buildings. So, based on the quality of the building, the commercial building can be categorized as 5-star building, or 3-star building, and also a general occupancy type of building. Another very important type of commercial structure, which we see are the hotels. Hotel may be a full-service hotel, or a limited-service hotel, entertainment unit, like a casino, or a resort.
But from that, the commercial structure may be a special purpose structure, like a bar, or a car servicing center, a theater, etc. So, commercial spaces are important part of our community, and those are usually seen around the city, where people come together for purchase and selling of the finished products. So, commercial structures. So, commercial structures, it forms a very important type of building in our day-to-day activities. Now, we will move on to the next topic, that is introduction to industrial structures. So, industrial structures, what actually are industrial structures?
So, in an industrial facility, or any industrial facility, for example, a petrochemical facility, there are large number of processes carried out simultaneously, and this process requires power, it requires some input or raw material, and it requires some instrumentation or control sequence through which a proper process is carried out. So, in addition to that, it requires an output handling unit, or the output receiving unit. So, this large number of equipments in any industrial facility, they are connected through many pipes. This pipe facilitates the flow in and out of the equipment.
Apart from that, as I said earlier, the equipments require power. So, there are power cables to the equipment. Also, there is some instrumentation attached to the equipment to control the process, and many more items like firefighting devices, the control valves, etc. are attached to the equipment. So, to facilitate all this, there are support structures. The structure may support the equipment itself. Also, it may support the inlet and outlet piping. It may support the cable trays for electrical and instrumentation. Apart from that, these structures, which are called as industrial structures, they may also support the platforms and walkways, so as to assess the equipment in case any manual intervention is required.
So, the best example of an industrial structure is a pipe rack. We will be seeing the pipe rack in detail in the upcoming weeks. Another good example of an industrial structure is the technological structure. So, as you can see in the picture, it's the construction phase of one of the technological structure. You can see the equipments in white color and the steel structure, which is being directed. There are many platforms, ladders seen in the picture. So, they are to gain access to the equipments or to the wall, which need to be manually operated.
Also, these platforms are required for maintenance of the structures or the parts of the structure. Also, equipment and piping needs to be maintained in case of any fault in the process, where manual intervention is required to correct the fault. In that case, a person has to walk through the walkways at the desired part of that structure. Industrial structure may also be a building or a shed, which is an enclosed structure to protect the inside part or equipment from the open environment. Now, suppose in case, the external environment is very harsh, like it's very hot outside or very cold.
Then in that case, some processes or some equipments may be affected because of the climatic conditions. And in such case, the buildings or sheds are enclosed. Enclosed and in this enclosed space, the equipments are placed and these equipments are protected from the outside environment. There may be climate quality control, especially the temperature and humidity control, which is mandatory or essential for certain processes. So, thus, a building or a shed forms an important role in industrial structure. Apart from that, industrial facilities may have pipe racks, slippers or pipe crossings.
Even apart from that, there may be some equipment supporting structures and many more. Bridges, ports and terminals also forms the industrial structure. Bridges are required to connect the roads over a river or anything which causes endurance in the pathway. Ports and airports are required for ship navigation and air navigation. All these form the important industrial structure, which are strategically very important. And they form an valuable part of our mission. Now, for any industrial project, the project has to be carried out in various stages. And to carry out this project in a proper way, they are split into few stages.
We will see them as stages of project execution. So, basically, there are three phases of any industrial project execution. The very first being the proposal stage. Proposal stage is the very initial stage of the project in which the basic idea of the project is described. What are the basic inputs, outputs, capacity, location, size? So, overall footprint of the project is established in the proposal state. In the basic engineering stage, the cost estimation is carried out. A footprint is developed by using the basic thumb rules or industry practice.
And this forms the basis for the detailed engineering phase. And detailed engineering phase is the final plan for the project to be constructed. So, we will see one by one all these project execution stages. The very first stage, that is the proposal stage. This stage defines the following parameters. Is the project proposal. Project proposal may be the location of the proposal. The type of facility it is. And budget for that proposal. The timelines for the project. Any industrial project, it calls for heavy investment. And all these investments require a time-bound activity for a project to be completed.
Time is the essence of any project. Case of industrial projects. And therefore, the timelines need to be properly defined or practically defined. And the very next stage or parameter is the requirements. The basic requirements which defines a project are defined in the proposal stage. Those may be the quality of outputs or the type of output it is required from that facility. And the goals. The goals may be with respect to cost, with respect to timelines again. And also overall as a project. What needs to be achieved by developing this project is very well defined in this proposal stage.
And it is very critical with respect to the success of the project. To define the proposal stage is the most critical activity in any project. The primary goal is to complete a project proposal and plan and document it. So that there is much more clarity on the further path of the project. The next stage which follows the proposal stage is the basic engineering stage. Basic engineering phase is the conceptual design phase of the project. In this, the technical feasibility is carried out. Whether certain capacity of processes are really feasible or not that are ensured during this phase.
If those are not feasible, then there are alternative studies for various type of processes, equipment and type of technology which is being used. After selecting proper technology, studying all the technical aspects, the economic point of view is also analyzed in detail. And the cost-benefit analysis is done to ensure that the project is economically feasible. This basic engineering phase is also called as feed stage which is front-end engineering design. So in this basic engineering phase, There is the basic engineering package known as BEP which is delivered and which is very well documented.
So there are many more documents which form the part of this basic engineering phase or BEP. The very first is design basis. These design basis may be for various disciplines. Say design basis for civil, construction, design basis for piping, mechanical, electrical, instrumentation, process and also for projects and other disciplines. The PFDs that is the process flow diagram forms a very important document for this basic engineering package and using those process flow diagrams the PNIDs are developed. PNIDs are piping and instrumentation diagrams which show the flow of processes from equipments within the project.
Another important part of basic engineering package is the footprint of the project itself. Without the footprint nothing can be called as well established. So a layout or a plot plan is prepared during the basic engineering package and the plot plan showing all the important structures, equipment and layout of the plant forms the most important document of the engineering package or the basic engineering package. Apart from the layout, there is another important document which is called as the material takeoff or the data sheet. To arrive at the cost estimate of any project or say a tentative cost estimate of the project, we need to have the material takeoffs for all the key items which will be required to construct that project.
These include material takeoffs for equipments, piping, civil facilities and all other discipline facilities or parts. So the material takeoff along with the plot plan forms two major part of the project execution phase that is the basic engineering phase. And apart from that, the process flow diagrams and PNIDs support or help to develop the plot plan. Another important part of the BEP is the scope of work for the contractor. Because there may be many different contractors involved in one certain project for an industrial project. And the scope of each contractor, for example, the scope of civil contractor, the scope of piping contractor, this needs to be defined and well documented at this basic engineering phase.
And all these deliverables, the design basis, process flow diagram, PNIDs, plot plan, material takeoff and scope of work forms the complete package. In the basic engineering phase, the capacity with respect to the facility is well defined considering its feasibility technically as well as economically. Also in the basic engineering phase, the law of the land, that is the legislation and regulation is also ensured whether it is followed and found to be within that regulation. Anything which is not legal can't be expected to function in that location.
That's why legislation and local regulations also need to be accounted. The national building codes or national law also needs to be followed. For example, if a facility carrying out certain process, we need to see whether the pollution control norms are technically feasible to follow. Another important part of the basic engineering package is the manufacturing process and its requirement. Once any product or any output is required, the basic engineering document defines the manufacturing process and all its requirements. Say requirements like raw materials required and the capacities.
Another important part of this document is the installation procedure. Say there are N number of equipments in the facility for the desired process. So in that the installation needs to be specifically done. Apart from that, there are block diagrams and plans in addition to the footprint. So that the main goal of the project is conveyed through this block diagrams and plan. Any industrial facility has few ancillary services associated with it. So there is an estimate required for the ancillary services as well. Apart from that, once the process is well defined, we have the process flow diagrams and PNIDs.
The preliminary equipment list is prepared and this list forms the basis of the equipment cost evaluations at the later stage of the project. Now, any industrial facility is built to add value to the company's existing products or existing valuation. So an economic valuation of the investment that is studied and checked for its purpose, you can check whether the investment made in the facility is really profitable or what will be the returns on the investment. So that sort of investment analysis or economic analysis is also carried out in the basic engineering states.
Now, last but not the least forms the detail engineering phase. In the detail engineering phase, the complete project or the final design is achieved and the project is ready to be constructed or executed. After the feed stage, the project feasibility is already ensured and further building to the feed, the detail engineering phase comes. In the detail engineering phase, there are few components like to design, develop and detail the individual components of the project. The feed or the proposal data which was done in the earlier part of the project that forms the basis for the detail engineering phase and considering the basic data, it is designed and developed to form the final output.
This final output is in the form of construction drawings and issued to the contractors and with those construction drawings, which are popularly called as issued for construction drawing, IFC drawings, actual construction is possible. Once the design is finalized and all the drawings are ready or part drawings of the project are ready, they can be issued to the contractor and on simultaneously, the final material takeoff can be calculated or arrived at. Once the final material takeoff is available, the cost estimate can be perfectly found out. So after the detail engineering phase, the exact cost of the project can be determined.
The detail engineering phase start after the feed handover or after the feed ends and it ends at the stage when all the construction drawings are issued to the construction contractor. This includes final P&IDs, final civil construction drawings, final equipment list and the empty years.