Week 7 Challenge - Assembly Workbench
Aim : To create Assembly for Given 2D Drawing and Drafting
QUICK RETURN MECHANISM
PARTS
- MAIN FRAME
- BLOCK
- SLIDER
- DHAFT
- ARM
MAIN FRAME
Sketch

Thickness

Sketch

Removed material through boolean operation

Tree Structure


Block
Sketch

Pad

Skecth to remove material

Material removed throug boolean operations

Tree Structure

Arm
Sketch

Pad

Sketch to add material

Material added through boolean operations

Tree Structure

Slider
Sketch

Pad

Sketch to remove material

Material removed through boolean operation


Tree Structure

Shaft
Sketch

Pad

Tree Structure

ASSEMBLY

DRAFTING






CONSTANT VELOCITY JOINT
PARTS CREATION AS PER 2D DRAWING
In Constant Velocity Joint there toal 3 Parts
- Block 01
- Block 02
- Block 03
Creating Block 01
Sketches

Pad

Sketch 2

Pad 2

Edge Fillet

Tree Structure

Block 02
Sketch

Pad

Sketc 2 to remove material

Removed material through boolean operations

Created plane and drawn sketch repeated same procedure

Sketh 5

Pad

Done union trim and added material removed unwanted faces

Given edge fillet 2.5mm

Tree Structure


BLOCK 03
Sketch

Pad

Sketch to remove material

Used boolen operation to remove material

Copyied above part body and done symmetry with respect to YZ plane

Sketch 3

Pad

Sketch to remove maerial

Removed material by using boolean operation

Used union trim command and removed unwanted faces

Edge fillet 2mm

Tree Structure



CV Joint Assembly

Drafting




CONCLUSION
Assembly is created as per the drawing given and drafting is done.