Challenge

To calculate dead and live load for industrial steel structures and to apply them using TSD

1.Aim:

To Calculate dead load in design report based on IS code and apply dead load on the model.

Given data:

  • Finishes of 50mm
  • Slab as per design
  • Brick wall 150mm thickness
  • Roofing load based on purlin size
  • Ceiling loading 0f 0.3KN per sq m

Procedure:

  • Open the TSD file which is been modelled for the last challenge.

To model slab:

  • Go to Home -> Manage property sets-> New -> General slab items
  • Rename it as S1 and give the following property for One- way slab
  • Go to Home -> Manage property sets-> New -> General slab items
  • Rename it as S2 and give the following property for Two - way slab
  • Take the dimensions to choose the slab types from the above creation.

Modeling slab:

  • Go to G.L and select Model -> Slabs on beams and select Slab on beams and appropriate slab property in the property window.
  • Click inside the grid where it’s needed.
  • Follow the same procedure for first floor level but keep the stair area free.
  • Go to Top of Roof Beam Level and follow the above procedure.
  • Go to 3D view to view as a whole.
  • Validate the model.
  • Go to Load -> Load cases and add the following loads as required by clicking add button in the loading dialog box.
  • Go to Load -> Load combination - > Generate and select the following option.
  • Open MS Excel and do the load calculation for Dead load as shown below.
  • In TSD, Go to Ground level select load as Dead in the drop down below.
  • Go to Load -> Area load, enter value as 1.2 KN/m2 in the property.
  • Click on each slab
  • Validate the model and proceed.
  • Go to First floor level and follow the same procedure.
  • Go to Top of Roof Beam Level and follow the same procedure.
  • Go to 3D view to check and validate.
  • Go to GL and apply the brick loading by selecting load -> Full UDL and entering 15.6 KN/ m in the property window and select the perimeter of the model.
  • Go to load -> Line load and enter the value and pick a reference node and draw brick loading line by referring the plan.
  • Again, go to load -> Full UDL and select the remaining members in the GL.
  • Toggle to 3D view and validate.
  • Follow the above procedure for First floor level.
  • Follow the above procedure for T.O.R.B level.
  • Go to 3D view and apply roof loading by selecting load ->Area loading and enter the value in the property window.
  • Result:
  • Dead load is applied by following above steps.

2.Aim:

To calculate live load in design report based on IS code and apply live load on the model.

Given data:

  • Assume the loading based on IS 875
  • Roof loading
  • Consider equipment loading as 5KN per sq m.

Procedure:

  • Refer IS 875 Part -2,Table- 1 for Live load
  • Open EXCEL and enter the loads and values to be used in the project for easy check.
  • Open TSD steel building model.
  • Go to Ground level
  • Select the load as imposed load in the status drop down.
  • Go to Load -> Area load and click on the slab.
  • Check the excel and enter the loading in the property window and follow the same procedure for the rest of the slabs.
  • Toggle to 3D view and validate.
  • Go to first floor level and do the loading.
  • Go to Top of the Roof Beam Level and change the loading to Imposed and assign the load.
  • Go to 3D and change the loading to Imposed and apply the load on the roof.
  • Result:
  • Validated result.
  • Imposed load is applied by following above steps.

3.Aim:

To generate a calculation for 5T crane loading based on given inputs.

Given data:

  • Centre to Centre of wheel = 10m
  • Weight of crab = 40 KN
  • Number of wheels = 4
  • Wheel base = 2m

Calculation:

  • The approximate minimum approach of the hook to gantry girder = 1m
  • Crane capacity = 5T=5000kg= 50000 N = 50KN
  • No of wheels on each side = 2
  • Span of Gantry girder, c/c distance between column = 7m

Maximum wheel load

  • Maximum concentrated load on crane =Crane capacity + Crab weight 50 +40 = 90 KN.
  • Self-weight of Crane=60 KN.
  • UDL on crane =60/10 = 6 KN/m
  • Ra +Rb = 90 + (6*10) =150KN
  • Taking moment on b,
  • (Ra*10) – (90*9) – (6 *10*5) =0
  • Ra = 111KN
  • Rb =150 – 111 = 39 KN
  • Taking max reaction, Static wheel load= 111KN.
  • This load is shared by 2 wheels, so 111/ 2 = 55.5 KN
  • Adding 10 % of impact = 55.5 *1.1 = 61.1 KN
  • Factored load = 61.1 * 1.5 = 91. 65 KN

Maximum Bending moment :

  • Assume Self weight of the gantry girder = 1.6 KN/m
  • Self-weight of the Rail= 0.3 KN/m
  • Total UDL = (Self – weight of rail+ self-weight of gantry girder)= 1.6 +0.3=1.9 KN/m.
  • Ra +Rb = (91.65 *2) + (1.9* 7) = 196.6 KN
  • Moment at B =0
  • (Ra*7) – (91.65 * 2 ) – ( 91.65 * 4) – ( 1.9 *7* 3.5) = 0
  • Ra = 85.20 KN
  • Rb = 111.4 KN
  • Bending moment under wheel due to live load = 85.20 *4 = 340.8 KN
  • Bending moment due to impact = 0.10 * 340.8 = 34.08 KNm
  • Total bending moment due to live load and impact load =340.8 +34.08 =374.88 KNm

Maximum shear force in gantry girder:

  • For the maximum SF in gantry girder, one of the wheel loads have to be placed on the support.
  • Moment at B= 0
  • (7* Ra ) –( 91.65 *7) –( 91.65 *5) –( 1.9*7*3.5)=0
  • Ra = 163.76 KN
  • The maximum shear force due to wheel load is 163.76 KN

Lateral force:

  • Surge load along y = 10% of (crane capacity + crab load) = 0.1 * ( 50+40) =9KN
  • This load is shared by 4 wheels = 9/4 = 2.25 KN
  • Maximum horizontal reaction due to the lateral force by proportion at
  • = Lateral force * reaction at a due to vertical load / maxiu,m wheel load due to vertical load
  • = 2.25 * 85.20/ 91.65 = 2.09 KN
  • At B
  • 9- 2.09 = 6.91 KN
  • Brake load along X = 5% of static wheel load = 0.05 * 111 = 5.55 KN

Result:

Hence the maximum wheel load, bending moment, shear force, Surge and brake load are found.

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.