To calculate dead and live load for industrial steel structures and to apply them using TSD
Aim: To Calculate dead load in design report based on IS code and apply dead load on the model
Procedure:
Load calculations:
- Dead Load=
">1.2knm21.2knm21.2 k n m 2 - Finishes=500mmx24
">knm3knm3=k n m 3 ">1.2knm21.2knm21.2 k n m 2 - Brick wall load =0.15x20x5.2=15.6
">knm2knm2(Ground to intermediate floor)k n m 2 - Brick wall load =0.15x20x6.8=20.5
">knm2knm2(intermediate floor to Roof )k n m 2 - Brick wall load =0.15x20x4.8=14.5
">knm2knm2(Roof to top floor)k n m 2 - Roof load =
">1.5knm1.5knm1.5 k n m - ceiling load=
">0.3knm0.3knm0.3 k n m
- Now go-to model tab and select slabs on beams option as shown


- Now we get a window named as loading as shown

- Now add required loads in this window

- Now Goto load tab and select combinations

- Now we get a window named as loading as shown

- Now click on combinations and add required combinations as shown below

- Now select the level where we want to apply the loads
- Now select the loads as required at the bottom left corner

- Now go to the load tab and select the Area to apply load on the slab

- Now we can see the Area load applied on the slab

- Now select the level where we want to apply the loads
- Now select the loads as required at the bottom left corner

- Now go to the load tab and select the UDL to apply load on the brick wall

- Now we can see the UDL applied on the brick wall

- Finally, apply loads on the Roof

Result:
Calculation of dead load in design report based on IS code and application of dead load on the model is done.
2 ans:
Aim: To Calculate live load in design report based on IS code and apply live load on the model
Procedure:
Based on the IS 875 the live loads are applied, as follows.
- Workshop = 5
">knm2knm2k n m 2 - Staircase =5
">knm2knm2k n m 2 - Corridor = 5
">knm2knm2k n m 2 - Meeting Room = 5
">knm2knm2k n m 2 - Store Room =5
">knm2knm2k n m 2 - Toilet = 2
">knm2knm2k n m 2 - Canteen = 3
">knm2knm2k n m 2 - Office Room = 3
">knm2knm2k n m 2 - Conference Room = 5
">knm2knm2k n m 2 - Equipment Room = 10
">knm2knm2k n m 2 - Rest Room = 2
">knm2knm2k n m 2 - Administration Room = 5
">knm2knm2k n m 2
The Live loads are applied for all the floors, as shown below.
- Now select the level where we want to apply the loads
- Now select the loads as required at the bottom left corner

- Now go to the load tab and select the Area to apply load on the slab

- Now we can see the Area load applied on the slab

Result:
Calculation of live load in design report based on IS code and application of live load on the model is done.
3 ans:
Aim: Generate a calculation for 5T crane loading based on the following inputs
Procedure:
Given Data:
- Centre to Centre of wheel = 10m
- Weight of crab = 40 KN
- Number of wheels = 4
- Wheelbase = 2m
- Crane Capacity=50 KN
- weight of trolley = 10kN
- hook approach = 1m
Maximum point load on Crane=Crane capacity + weight of the trolley
=50+10
=60KN
UDL=
=40/14
=2.89KN/m
Moment at A:

=60x1-RBX14+2.89X14X14/2
RB=24.5KN
RA+RB-60-2.89X14=0
RA=60+2.89X14-RB
RA=75.9KN
Now assuming self weight of gantry grider=1.2 KN/m
assuming self weight of gantry grider=0.3KN/m
Total self weight=1.2+0.3
=1.5KN/m
FACTORED LOAD=1.5X1.5
=2.25KN/m
Now load on each wheel=75.9/2
=37.97KN
Factored load=37.97x1.5
=56.95KN
=57KN
Moment at C:

RDx6=2.25x6x6/2+57x4.5+57x2.5
RD=73.25KN
RC+RD-57-57-2.25X6
RC+RD=127.5KN
RC+73.25=127.5
RC=127.5-73.25
RC=54.25KN
MAX SHEAR FORCE

REX6-57-57X4-2.25X6X6/2=0
RE=101.75KN
IMPACT LOAD:
=10% OF WHEEL LOAD
=0.1X101.75
=10.175KN
V=Wl/2
=
=4.5KN
Max shear force=4.5+10.175+101.75
=116.425KN
Lateral load analysis=5% of total weight
=
=3KN