Challenge

Project 2 - A project on creating Key Performance Indicator (KPI) dashboard for an Automotive Manufacturing company

1 ANSWER OEE=Availability*Performance*quality
Avalability = (Run Time / Planned Production time)*100
Performance = (Ideal cycle time*Total Count)/Run time)*100
Quality= (Total count-Reject Count )/Total Count)*100
2 ANSWER
Uptime = Run-Time (Production) ÷ Total Available Time
Production Run-Time = Total Available Time to Run – Scheduled and Unscheduled Downtime
Defective units ÷ (total units per 1,000)
First Time Through (FTT) = Total Units Produced – Defective Units) ÷ Units Produced
OEE is a manufacturing KPI that combines line availability, performance efficiency and quality of a specific line, equipment or process. Management commonly evaluates this KPI to compare performance among similar or identical machines, lines, or plants. OEE is a ratio usually expressed as a percentage.
Calculate OEE by multiplying the three factors: plant availability, performance efficiency, and FTT/quality.
Availability = Uptime/Planned Production Time
Run Time = Planned Production Time – Downtime
Performance = (Ideal Cycle Time × Total Count) ÷ Run Time
Ideal Cycle Time (Takt Time) = Ideal/expected cycle time that your process should achieve
Quality = Good Count ÷ Total Count
Total Count = Good + Defective + Scrap
Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.