Challenge

Project 1

Step1: Make the EPS as “Skill-Lync Education” and OBS and assign a Project Manager

Enterprise Project Structure (EPS): Skill-Lync Education

  • This is the top-level organizational structure under which various projects will be managed.

Organizational Breakdown Structure (OBS):

  • Assign a Project Manager to oversee the Skill-Lync Education Centre project.

Step2: Create project under the above EPS named “ Skill-Lync Education Centre”

  • Project Name: Skill-Lync Education Centre
  • Project Start Date: 1st October 2020
  • Project End Date: 30th April 2023
  • Project Manager: [Assigned Project Manager from OBS]
  • Work Hours: 24 hours a day, 6 days a week

Step3: Create at least 50 activities.

Step4: Break Major WBS as - Initial Activities , Design , Construction and Balance Works

Step5: Use all FS , SS , FF and lags suitably

Activity ID Activity Name Original Duration Relationship Type Lag
Not Started 807d
A1000 Project Kickoff Meeting 5d
A1010 Form Project Team 10d FS
A1020 Develop Project Management Plan 10d FS
A1030 Site Survey and Analysis 10d FS
A1040 Soil Testing 5d FF 2d
A1050 Obtain Zoning Approval 10d FS
A1060 Obtain Building Permits 5d FS
A1070 Environmental Impact Assessment 10d FS
A1080 Conceptual Design 15d FS
A1090 Preliminary Design Review 10d FS
A1100 Detailed Design 15d FS
A1110 Design Approval 10d FF 2d
A1120 Structural Engineering 25d FS 10d
A1130 MEP Design 12d FS
A1140 Design Coordination 15d SS 10d
A1150 Approvals 10d FF 5d
A1160 Concept Development 15d FS 10d
A1170 Detailed Design 20d FS
A1180 Design Review 20d SS 10d
A1190 Approval 10d FF 5d
A1200 Architectural Drawings 15d FS, FS 5d, 5d
A1210 Structural Drawings 15d SS 7d
A1220 MEP Drawings 15d SS 5d
A1230 Furniture and Interior Drawings 15d SS 8d
A1240 Approvals 15d FF 8d
A1250 Area Clearing and Excavation 10d FS
A1260 PCC and Footing Concrete 15d FS
A1270 Plinth beams and Column upto FGL 18d FS
A1280 Filling Upto FGL 7d FS
A1290 Ground Floor Casting 35d FS
A1300 Column Concrete Upto 1st Floor 10d FS
A1310 First Floor Staircase, Beam And Slab Casting 45d SS 5d
A1320 Second Floor Column Casting 18d FS
A1330 Second Floor Staircase, Beam And Slab Casting 50d SS 7d
A1340 Column Concrete Upto Roof Level 18d FS
A1350 Roof Floor Staircase, Beam And Slab Casting 45d SS 5d
A1360 Mumty Slab Casting 30d FS
A1370 Boundary Wall Around school building 90d FS
A1380 Masonary Work - Ground Floor 35d FF, FF 20d, 100d
A1390 Masonary Work - First Floor 35d FS, FF 40d
A1400 Masonary Work - Second Floor 30d FS, FF 0d, 5d
A1410 Painting 30d FS,FS
A1420 Flooring 30d FS,FS
A1430 Door and Window Fixing 25d FS
A1440 Electrical Wiring , Plumbing Installation 20d FS
A1450 Parking Lot Construction 12d FS
A1460 Internal Road Construction 8d FS
A1470 Landscaping 10d FS
A1480 Playground Installation 10d FS
A1490 External Lighting 5d FS
A1500 Snagging and Rectification 7d FS
A1510 Final Cleaning 8d FS
A1520 Final Inspection 5d FS

Step7: Filter all critical activity

Activity ID Activity Name
Skill-Lync Education Centre G+2
Project Initial Activities
Initiation
A1000 Project Kickoff Meeting
A1010 Form Project Team
A1020 Develop Project Management Plan
Site Preparation
A1030 Site Survey and Analysis
A1040 Soil Testing
Permits and Approvals
A1050 Obtain Zoning Approval
A1060 Obtain Building Permits
A1070 Environmental Impact Assessment
Design
Architectural Design
A1080 Conceptual Design
A1090 Preliminary Design Review
A1100 Detailed Design
Structural and MEP Design
A1120 Structural Engineering
A1130 MEP Design
A1140 Design Coordination
Furniture and Interior Design
A1160 Concept Development
A1170 Detailed Design
A1180 Design Review
A1190 Approval
Finalize Construction Drawings
A1200 Architectural Drawings
A1210 Structural Drawings
A1220 MEP Drawings
A1230 Furniture and Interior Drawings
A1240 Approvals
Construction
Substructure
A1250 Area Clearing and Excavation
A1260 PCC and Footing Concrete
A1270 Plinth beams and Column upto FGL
Superstructure
A1280 Filling Upto FGL
A1290 Ground Floor Casting
A1300 Column Concrete Upto 1st Floor
A1310 First Floor Staircase, Beam And Slab Casting
A1320 Second Floor Column Casting
A1330 Second Floor Staircase, Beam And Slab Casting
A1340 Column Concrete Upto Roof Level
A1350 Roof Floor Staircase, Beam And Slab Casting
A1360 Mumty Slab Casting
A1370 Boundary Wall Around school building
Architectural
A1400 Masonary Work - Second Floor
A1410 Painting
A1420 Flooring
A1430 Door and Window Fixing
A1440 Electrical Wiring , Plumbing Installation
Balance Works
Parking Facility and Internal Roads
A1450 Parking Lot Construction
A1460 Internal Road Construction
Landscaping and External Works
A1470 Landscaping
A1480 Playground Installation
A1490 External Lighting
Final Touch-ups and Inspections
A1500 Snagging and Rectification
A1510 Final Cleaning
A1520 Final Inspection

Step7: There shall be no activity with more than 35 days float

Step8: Determine Early / Late - Start / Finish dates

Step9: At Least 2 activities must have constraints (Excluding start)

Step10: Assign a user defined field suitably

Step11: Some predecessors may be discretionary but realistic

Activity ID Activity Name Original Duration Total Float Predecessors Predecessor Details Successors Successor Details
Skill-Lync Education Centre G+2 807d 0d
Project Initial Activities 62d 0d
Initiation 25d 0d
A1000 Project Kickoff Meeting 5d 0d A1010 A1010: FS
A1010 Form Project Team 10d 0d A1000 A1000: FS A1020, A1030 A1020: FS, A1030: FS
A1020 Develop Project Management Plan 10d 0d A1010 A1010: FS A1030 A1030: FS
Site Preparation 12d 0d
A1030 Site Survey and Analysis 10d 0d A1010, A1020 A1010: FS, A1020: FS A1040 A1040: FF 2d
A1040 Soil Testing 5d 0d A1030 A1030: FF 2d A1050 A1050: FS
Permits and Approvals 25d 0d
A1050 Obtain Zoning Approval 10d 0d A1040 A1040: FS A1060 A1060: FS
A1060 Obtain Building Permits 5d 0d A1050 A1050: FS A1070 A1070: FS
A1070 Environmental Impact Assessment 10d 0d A1060 A1060: FS A1080 A1080: FS
Design 208d 0d
Architectural Design 42d 33d
A1080 Conceptual Design 15d 0d A1070 A1070: FS A1090 A1090: FS
A1090 Preliminary Design Review 10d 0d A1080 A1080: FS A1100 A1100: FS
A1100 Detailed Design 15d 0d A1090 A1090: FS A1110, A1120 A1110: FF 2d, A1120: FS 10d
A1110 Design Approval 10d 33d A1100 A1100: FF 2d A1130 A1130: FS
Structural and MEP Design 55d 5d
A1120 Structural Engineering 25d 0d A1100 A1100: FS 10d A1130 A1130: FS
A1130 MEP Design 12d 0d A1110, A1120 A1110: FS, A1120: FS A1140 A1140: SS 10d
A1140 Design Coordination 15d 0d A1130 A1130: SS 10d A1150, A1160 A1150: FF 5d, A1160: FS 10d
A1150 Approvals 10d 5d A1140 A1140: FF 5d A1160 A1160: FS
Furniture and Interior Design 50d 0d
A1160 Concept Development 15d 0d A1140, A1150 A1140: FS 10d, A1150: FS A1170 A1170: FS
A1170 Detailed Design 20d 0d A1160 A1160: FS A1180 A1180: SS 10d
A1180 Design Review 20d 0d A1170 A1170: SS 10d A1190, A1200 A1190: FF 5d, A1200: FS 5d
A1190 Approval 10d 0d A1180 A1180: FF 5d A1200 A1200: FS 5d
Finalize Construction Drawings 43d 0d
A1200 Architectural Drawings 15d 0d A1180, A1190 A1180: FS 5d, A1190: FS 5d A1210 A1210: SS 7d
A1210 Structural Drawings 15d 0d A1200 A1200: SS 7d A1220 A1220: SS 5d
A1220 MEP Drawings 15d 0d A1210 A1210: SS 5d A1230 A1230: SS 8d
A1230 Furniture and Interior Drawings 15d 0d A1220 A1220: SS 8d A1240 A1240: FF 8d
A1240 Approvals 15d 0d A1230 A1230: FF 8d A1250 A1250: FS
Construction 502d 35d
Substructure 43d 0d
A1250 Area Clearing and Excavation 10d 0d A1240 A1240: FS A1260 A1260: FS
A1260 PCC and Footing Concrete 15d 0d A1250 A1250: FS A1270 A1270: FS
A1270 Plinth beams and Column upto FGL 18d 0d A1260 A1260: FS A1280 A1280: FS
Superstructure 319d 0d
A1280 Filling Upto FGL 7d 0d A1270 A1270: FS A1290 A1290: FS
A1290 Ground Floor Casting 35d 0d A1280 A1280: FS A1300 A1300: FS
A1300 Column Concrete Upto 1st Floor 10d 0d A1290 A1290: FS A1310 A1310: SS 5d
A1310 First Floor Staircase, Beam And Slab Casting 45d 0d A1300 A1300: SS 5d A1320, A1390 A1320: FS, A1390: FS
A1320 Second Floor Column Casting 18d 0d A1310 A1310: FS A1330 A1330: SS 7d
A1330 Second Floor Staircase, Beam And Slab Casting 50d 0d A1320 A1320: SS 7d A1340, A1400 A1340: FS, A1400: FS
A1340 Column Concrete Upto Roof Level 18d 0d A1330 A1330: FS A1350 A1350: SS 5d
A1350 Roof Floor Staircase, Beam And Slab Casting 45d 0d A1340 A1340: SS 5d A1360 A1360: FS
A1360 Mumty Slab Casting 30d 0d A1350 A1350: FS A1370, A1410, A1380 A1370: FS, A1410: FS, A1380: FF 20d
A1370 Boundary Wall Around school building 90d 0d A1360 A1360: FS A1420, A1380, A1400 A1420: FS, A1380: FF 100d, A1400: FF 5d
Architectural 165d 35d
A1380 Masonary Work - Ground Floor 35d 35d A1370, A1360 A1370: FF 100d, A1360: FF 20d A1390 A1390: FF 40d
A1390 Masonary Work - First Floor 35d 35d A1310, A1380 A1310: FS, A1380: FF 40d
A1400 Masonary Work - Second Floor 30d 0d A1370, A1330 A1370: FF 5d, A1330: FS A1410 A1410: FS
A1410 Painting 30d 0d A1400, A1360 A1400: FS, A1360: FS A1420 A1420: FS
A1420 Flooring 30d 0d A1410, A1370 A1410: FS, A1370: FS A1430 A1430: FS
A1430 Door and Window Fixing 25d 0d A1420 A1420: FS A1440 A1440: FS
A1440 Electrical Wiring , Plumbing Installation 20d 0d A1430 A1430: FS A1450 A1450: FS
Balance Works 65d 0d
Parking Facility and Internal Roads 20d 0d
A1450 Parking Lot Construction 12d 0d A1440 A1440: FS A1460 A1460: FS
A1460 Internal Road Construction 8d 0d A1450 A1450: FS A1470 A1470: FS
Landscaping and External Works 25d 0d
A1470 Landscaping 10d 0d A1460 A1460: FS A1480 A1480: FS
A1480 Playground Installation 10d 0d A1470 A1470: FS A1490 A1490: FS
A1490 External Lighting 5d 0d A1480 A1480: FS A1500 A1500: FS
Final Touch-ups and Inspections 20d 0d
A1500 Snagging and Rectification 7d 0d A1490 A1490: FS A1510 A1510: FS
A1510 Final Cleaning 8d 0d A1500 A1500: FS A1520 A1520: FS
A1520 Final Inspection 5d 0d A1510 A1510: FS

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.