Challenge

Project 1

Step 1:

Make the EPS as “Skill-Lync Education” and OBS and assign a Project Manager

* Enterprise tab > OBS > add ( new > project manager )

*Enterprise > EPS >Skill -Lync education 

*Assign > OBS ( project manager )

*Click okay 

project us created under EPS " Skill-Lync Education Centre"

*Project will start on 1st October 2020 and end by 30th April 2023.

Create at least 50 activities.

*Break Major WBS as - Initial Activities, Design, Construction, and Balance Works

*Click on WBS ( Right side of the project )

*The details are added 

Now adding the sub-topics 

 *Further Breakdown Construction into Substructure, Superstructure, and Architectural

Now go activities > and 50 activities are added 

All activity Id’s are having  an interval of exactly 10

*the duration is changed to approximate dates 

 predecessor/successor choose suitable relationship of each activity is added 

*Using the column option the predecessor and successor are added 

Work hours will be 24 hours and 6 days a week are added 

*Complete Design in 8 months

Select the Schedule tool on top of the tool bar

*therefore  the  Early/Late start and finish has been determined successfully

he constraints are done using the bottom > status tab 

Your portfolio, next

Ship work like this
in your own course.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.