Identification of Cracks
Q1)
a- Observation:-
- Concrete crushed and the reu=inforsment is exposed
- Concrete spalled beyond the reinforcement which may be a sign of rupture.
- Beam top portion looks safe because of the flange advantage from slab.
- The Crack develops from bottom to top means rebar yielding occurs in support bottom only
Answer:-
- Its form of flexural failure due to reversal of stress during an earthquake
- During stress reversal. Support top exeriencess compression and bottom experiences tension
- top compression is managed by slab advantage. bottom tension was not satisfied by the provided reinforcement
- Since the reinforcement was yielded it can not be repaired
b- Observation:-
- Cranks along beam column edge.
- Cracks seem to have developed through the structure as it looks much wider
- Beam looks separated from the column at joints
- concrete is not severely crushed
Answer:-
- Its beam pull-out failure due to insufficient development length of reinforcement in joints
- During earthquake the horizontal movement of the structure makes this condition worse and detaches the beam member from the column
- Providing anchoring length between two existing concrete is very difficult. So not repairable
C- Observation:-
- Cracks are exactly at the joint of the column beam.
- Cracks in Beam developed through its entire width.
- The slab also developed more cracks along the beam width direction.
Answer:
- It's a Plastic hinge failure.
- The damage occurred only in the joint zone first of all.
- Cyclic lateral loading & stress reversal at the joints led to the damage.
- Even the slab participated to its best to handle the Tension (Slab is severely cracked means it has undergone tension with its flange condition), But unable to control the damage.
- The joint can be strengthened.
2) a- Observations:
- Concrete damaged at top of a Column.
- Concrete damaged all around the Column face.
- Beams are safe.
- The location of column looks at edge of the building.
- No walls are built along the column means it is probably at Ground floor, for Parking Car movement access.
Answer:
- It's a Soft storey failure, Technically Plastic hinge formation.
- Due to absence of Infill walls at the Ground floor, The plastic hinge forms at the Top of ground storey columns during Lateral movement.
- Based on the development of crush of concrete, it can either be repairable or Non-repairable.
b) Observations:
- Concrete developed complete breakage diagonally.
- Longitudinal reinforcements are intact.
- Shear reinforcement spacing looks wider (which means probably lesser shear rebar provided)
Answer:
- It's a Pure Shear failure.
- Inadequate shear reinforcement compels concrete takes all the shear stresses.
c) Observations:
- Column failed completely.
- Failure at top of column.
- There are two slabs connected to the column, Probably one at mid height of the column.
- The wooden piles might be a Post failure support after column failed, providing temporary prop to avoid collapse of the entire structure.
Answer:
- It's a Short Column failure.
- An additional slab or a Beam connected to a Column in mid-height leads to this effect.
- This leads to failure especially if the connection is unintentional and not accounted in design.
- The failure given in the picture is not at all repairable.