Identification of Cracks
1. a)
OBSERVATIONS :
- Concrete crushed and the reinforcement is exposed.
- Concrete spalled beyond the reinforcement which may be a sign of rupture.
- Beam top portion looks safe because of the flange advanatage from slab.
- The crack develops from bottom to top means rebar yilding occurs in support bottom only.
ANSWER : - It's form of flexural failure due to reversal of stress during earthquake.
- During stress reversal,support top experiences compression and bottom experiences tension.
- Top compression is managed by slab advantage.Bottom tension was not satisfied by the provided reinforcement.
- Since the reinforcement got yielded,it can not be repaired.
b)
OBSERVATIONS : - Cracks along Beam - Column edge.
- Cracks seem to have developed through the structure as it looks much wider.
- Beam looks separated from the column at joints.
- Concrete is not severely crushed.
ANSWER : - It's Beam pull out of failure due to insufficient development length of reinforcement in joints.
- During earthquake,The horizontal movement of structure makes this condition worse and detached the beam member from column.
- Providing anchorage length between two existing concrete is very difficult.So not repairable.
c)
OBSERVATIONS : - Cracks are exactly at the joint of Column-Beam.
- Cracks in beam developed through its entire width.
- Slab also developed more cracks along the beam width direction.
ANSWER : - It's a plastic hinge failure.
- The damage occurred only in the joint zone.
- Cyclic lateral loading and stress reversal at the joints led to the damage.
- Even the slab participated to its best to handle the Tension (slab is severely cracked means it has undergone tension with its flange condition),But unable to control the damage.
- The joint can be strengthened.
2.a)
OBSERVATIONS : - Concrete damaged at top of a column.
- Conrete damaged all around the column face.
- Beams are safe.
- The location of column looks at edge of the building.
- No walls are built along the column means it is probably at Ground floor,for Parking Car movement access.
ANSWER : - It's a Soft storey failure,technically Plastic hinge formation.
- Due to absence of infill walls at the Ground floor,The plastic hinge forms at the Top of ground storey columns during Lateral Movement.
- Based on the development of crush of concrete,it can either be repairable or Non-repairable.
b)
OBSERVATIONS : - Concrete developed complete breakage diagonally.
- Longitudinal reinforcements are intact.
- Shear reinforcement spacing looks wider (which means probably lesser shear rebar provided)
ANSWER : - It's a Pure Shear failure.
- Inadequate shear reinforecement compels concrete takes all the shear stressess.
c)
OBSERVATIONS : - Column failed completely.
- Failure at top of column.
- There are two slabs connected to the column,Probably one at mid height of the column.
- The wooden piles might be a Post failure support after column failed,providing temporary prop to avoid collapse of the entire structure.
ANSWER : - It's a Short Column failure.
- An additional slab or a Beam connected to a column in mid-height leads to this effect.
- This leads to failure especially if the connection is unintentional and not accounted in design.
- The failure given in the picture is not at all repairable.