One recording of about 42 minutes from a live civil engineering workshop (published March 2023), narrated over slides. It introduces construction projects and the planning engineer's role, project planning, why monitoring matters and how progress is updated, then three techniques: the Gantt chart, the S-curve and earned value management.

23 chapters · published 1 Mar 2023 · 1,215 views as of 21 Nov 2026 · by Skill-Lync

Free. We ask for your name and phone once before it plays here · or watch on YouTube ↗

Who is this course for?

Civil engineering students and site or planning engineers who want an introduction to how construction project progress is planned, tracked and reported.

What will you learn?

  • Describe what a planning engineer prepares and tracks: work schedule, logistics plan, manpower histogram, milestones and drawing revisions
  • List what the planning phase produces: scope broken into deliverables and activities, plus quality, budget, risk, communication and procurement plans
  • Explain why monitoring compares quantity, cost and scope against a baseline schedule, with a concreting example
  • Read a planned-versus-achieved format for daily, weekly and monthly progress
  • Read a Gantt chart with progress bars and an S-curve of planned and actual cumulative values
  • Name planned value, actual cost and earned value, and how CPI and SPI below 1 are read

What does each part of the course cover?

7 sections, in watching order. Click a timestamp to jump the player there. The video description has no chapter list, so these chapters and timestamps were written from the video itself.

  1. 0:004 min · 3 chapters

    Construction projects and the project team

    Opens with the agenda and defines a construction project, with building, airport, metro, road, dam and renewable energy examples. Then shows the project team under a project manager, with the planning engineer and cost controller in the PMO, and why monitoring sits with the planning engineer.

    Chapters
    • 0:00Welcome, agenda and what the session covers
    • 1:38Construction projects: buildings, infrastructure and energy projects
    • 2:38The project team: PMO, construction and contracts, and why the planning engineer is highlighted
  2. 3:546 min · 5 chapters

    What a planning engineer does

    Lists the planning engineer's duties: the construction work schedule, inputs for the logistics plan, manpower histogram and milestone schedule, drawing revision tracking, and work done versus billing. Also covers a critical issues dashboard, the five life-cycle phases, handover status and recording project learnings.

    Chapters
    • 3:54Planning engineer's role: work schedule, logistics plan, manpower histogram, milestones
    • 5:29Tracking drawing revisions against each activity
    • 6:18Work done versus billing, weekly and monthly targets, keeping progress up to date
    • 7:43Critical issues dashboard, the five life-cycle phases and project handover status
    • 9:03Cost and productivity ideas, and recording project learnings
  3. 10:055 min · 3 chapters

    Project planning basics

    Describes planning as the second life-cycle phase: break the scope into deliverables, list and organise activities, and consider stakeholders, risks and resources. Names the quality, budget, risk, communication and procurement plans, then reads a sample bridge project plan with planned and actual dates and a Gantt chart with critical activities in red.

    Chapters
    • 10:05Project planning: scope, deliverables and activities
    • 11:10What the planning phase produces: schedule, quality, budget, risk, communication and procurement plans
    • 13:24A sample bridge project plan and how a Gantt chart shows critical activities
  4. 15:296 min · 3 chapters

    Project monitoring and why it matters

    Explains monitoring and controlling as the phase that runs alongside execution, comparing progress with a baseline schedule such as 300 days from a start date. A concreting example shows that quantity, cost and scope are tracked together. The speaker then gives causes of project failure and the benefits of good monitoring.

    Chapters
    • 15:29What project monitoring is: baseline schedule versus execution
    • 17:04Monitoring quantity, cost and scope together: a concreting example
    • 18:24Why monitoring matters: causes of failure and the benefits of good monitoring
  5. 21:374 min · 2 chapters

    Updating progress against the plan

    Shows how the planning engineer turns the schedule into two-week look-ahead and monthly work plans, collects actuals from the site engineer, and reviews planned against achieved in daily, weekly and monthly reports. A sample format for three footings in January 2023 lists excavation, PCC, steel, shuttering and concrete targets.

    Chapters
    • 21:37Updating progress: two-week look-ahead and daily, weekly and monthly reports
    • 23:50A planned-versus-achieved format for footings, with a worked monthly target
  6. 26:037 min · 3 chapters

    Gantt charts and S-curves

    Introduces the Gantt chart with a house-construction example, where a bar's duration and a blue progress bar show how far an activity has got. Then the S-curve of cumulative values against time, worked with planned 1, 2 and 2.5 crore against actual 0.5, 1 and 2 crore, to see where and why progress lags.

    Chapters
    • 26:03Monitoring techniques: reading a Gantt chart with progress bars
    • 29:43The S-curve: cumulative cost or manpower against time
    • 30:43Worked S-curve: planned versus actual cumulative billing in crore rupees
  7. 33:219 min · 4 chapters

    Earned value management and recap

    Introduces earned value management as measuring against the baseline, with planned value, actual cost and earned value, and the cost and schedule variances and indices. The speaker reads CPI below 1 as over budget and SPI below 1 as behind schedule, then recaps Gantt chart, S-curve and earned value.

    Chapters
    • 33:21Earned value management: planned value, actual cost and earned value
    • 35:33Cost variance, schedule variance, CPI and SPI
    • 38:41Reading CPI and SPI: over or under budget, behind or ahead of schedule
    • 41:05Recap of Gantt chart, S-curve and earned value, and close

Is the Project Monitoring Techniques course really free?

Yes. All 42 min of it is free on Skill-Lync's YouTube channel, with no payment. To watch it on this page with the chapter guide, leave your name and phone number once; you can also watch it directly on YouTube. It was published on 1 Mar 2023 and had 1,215 views as of 21 Nov 2026. This page adds the chapter guide, a study plan and what to learn next.

How long does the Project Monitoring Techniques course take to finish?

The video runs 42 min across 23 chapters. That fits in one sitting of under an hour; plan roughly twice that if you practise each exercise as you go. The longest section is "Earned value management and recap" (9 min), so give it your full attention.

Does the free project monitoring course come with a certificate?

The video description has a "claim your certificate" link, which now opens this page. To ask about a certificate for this course, leave your name and phone number in the form below and a Skill-Lync counsellor will call you back. The paid Skill-Lync courses linked here include a certificate along with mentor-reviewed projects.

What should I learn after this course?

The next step is Construction Project Management Fundamentals (₹40,000), then Post Graduate Program in Construction Project Management (₹2,75,000). The free course teaches the concepts; the paid Skill-Lync courses add graded projects, mentor feedback and, in the PG programs, placement support.

What software do I need for this project monitoring workshop?

The video does not name any software, licence or prerequisite. It is a slide-based talk with sample images of a project plan, a Gantt chart and an S-curve, and no hands-on demo in a planning tool. The speaker starts from basic definitions, so it can be followed without prior planning experience.

What is an S-curve in project monitoring?

The speaker describes an S-curve as a graph that tracks project progress, with cost or manpower plotted cumulatively against time. In the worked example the planned curve rises by 1, 1 and 0.5 crore rupees over three months to 2.5 crore, while the actual curve reaches 2 crore. The gap between the two shows where work is lagging.

What does a planning engineer do, according to this workshop?

The speaker says the planning engineer prepares the construction work schedule, the inputs for the logistics plan, manpower histogram and milestone schedule, tracks drawing revisions, and monitors and updates progress against weekly or monthly plans. The planning engineer also keeps a critical issues dashboard, reports handover status and records project learnings.

Last updated 21 Nov 2026 · Course length, chapters, views and dates from the YouTube video on 21 Nov 2026 · Grow by Skill-Lync: free lessons from every course

Finished the course?

Ask about the certificate or your next course.

Leave your name and phone number. A Skill-Lync counsellor calls you back within one working day about the certificate for Project Monitoring Techniques and the course that fits where you want to work.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Free full course · Skill-Lync

Start watching

Free, no payment. Leave your name and phone once and the whole Project Monitoring Techniques course plays here, with every free lesson on Grow. A Skill-Lync counsellor may call you about the certificate or your next course.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.