Project monitoring with Gantt, S-curve and earned value: free, 42 minutes
One recording of about 42 minutes from a live civil engineering workshop (published March 2023), narrated over slides. It introduces construction projects and the planning engineer's role, project planning, why monitoring matters and how progress is updated, then three techniques: the Gantt chart, the S-curve and earned value management.
23 chapters · published 1 Mar 2023 · 1,215 views as of 21 Nov 2026 · by Skill-Lync
Free. We ask for your name and phone once before it plays here · or watch on YouTube ↗
Who is this course for?
Civil engineering students and site or planning engineers who want an introduction to how construction project progress is planned, tracked and reported.
What will you learn?
- Describe what a planning engineer prepares and tracks: work schedule, logistics plan, manpower histogram, milestones and drawing revisions
- List what the planning phase produces: scope broken into deliverables and activities, plus quality, budget, risk, communication and procurement plans
- Explain why monitoring compares quantity, cost and scope against a baseline schedule, with a concreting example
- Read a planned-versus-achieved format for daily, weekly and monthly progress
- Read a Gantt chart with progress bars and an S-curve of planned and actual cumulative values
- Name planned value, actual cost and earned value, and how CPI and SPI below 1 are read
What does each part of the course cover?
7 sections, in watching order. Click a timestamp to jump the player there. The video description has no chapter list, so these chapters and timestamps were written from the video itself.
- 0:004 min · 3 chapters
Construction projects and the project team
Opens with the agenda and defines a construction project, with building, airport, metro, road, dam and renewable energy examples. Then shows the project team under a project manager, with the planning engineer and cost controller in the PMO, and why monitoring sits with the planning engineer.
- 3:546 min · 5 chapters
What a planning engineer does
Lists the planning engineer's duties: the construction work schedule, inputs for the logistics plan, manpower histogram and milestone schedule, drawing revision tracking, and work done versus billing. Also covers a critical issues dashboard, the five life-cycle phases, handover status and recording project learnings.
Chapters
- 3:54Planning engineer's role: work schedule, logistics plan, manpower histogram, milestones
- 5:29Tracking drawing revisions against each activity
- 6:18Work done versus billing, weekly and monthly targets, keeping progress up to date
- 7:43Critical issues dashboard, the five life-cycle phases and project handover status
- 9:03Cost and productivity ideas, and recording project learnings
- 10:055 min · 3 chapters
Project planning basics
Describes planning as the second life-cycle phase: break the scope into deliverables, list and organise activities, and consider stakeholders, risks and resources. Names the quality, budget, risk, communication and procurement plans, then reads a sample bridge project plan with planned and actual dates and a Gantt chart with critical activities in red.
- 15:296 min · 3 chapters
Project monitoring and why it matters
Explains monitoring and controlling as the phase that runs alongside execution, comparing progress with a baseline schedule such as 300 days from a start date. A concreting example shows that quantity, cost and scope are tracked together. The speaker then gives causes of project failure and the benefits of good monitoring.
- 21:374 min · 2 chapters
Updating progress against the plan
Shows how the planning engineer turns the schedule into two-week look-ahead and monthly work plans, collects actuals from the site engineer, and reviews planned against achieved in daily, weekly and monthly reports. A sample format for three footings in January 2023 lists excavation, PCC, steel, shuttering and concrete targets.
- 26:037 min · 3 chapters
Gantt charts and S-curves
Introduces the Gantt chart with a house-construction example, where a bar's duration and a blue progress bar show how far an activity has got. Then the S-curve of cumulative values against time, worked with planned 1, 2 and 2.5 crore against actual 0.5, 1 and 2 crore, to see where and why progress lags.
- 33:219 min · 4 chapters
Earned value management and recap
Introduces earned value management as measuring against the baseline, with planned value, actual cost and earned value, and the cost and schedule variances and indices. The speaker reads CPI below 1 as over budget and SPI below 1 as behind schedule, then recaps Gantt chart, S-curve and earned value.
Is the Project Monitoring Techniques course really free?
Yes. All 42 min of it is free on Skill-Lync's YouTube channel, with no payment. To watch it on this page with the chapter guide, leave your name and phone number once; you can also watch it directly on YouTube. It was published on 1 Mar 2023 and had 1,215 views as of 21 Nov 2026. This page adds the chapter guide, a study plan and what to learn next.
How long does the Project Monitoring Techniques course take to finish?
The video runs 42 min across 23 chapters. That fits in one sitting of under an hour; plan roughly twice that if you practise each exercise as you go. The longest section is "Earned value management and recap" (9 min), so give it your full attention.
Does the free project monitoring course come with a certificate?
The video description has a "claim your certificate" link, which now opens this page. To ask about a certificate for this course, leave your name and phone number in the form below and a Skill-Lync counsellor will call you back. The paid Skill-Lync courses linked here include a certificate along with mentor-reviewed projects.
What should I learn after this course?
The next step is Construction Project Management Fundamentals (₹40,000), then Post Graduate Program in Construction Project Management (₹2,75,000). The free course teaches the concepts; the paid Skill-Lync courses add graded projects, mentor feedback and, in the PG programs, placement support.
What software do I need for this project monitoring workshop?
The video does not name any software, licence or prerequisite. It is a slide-based talk with sample images of a project plan, a Gantt chart and an S-curve, and no hands-on demo in a planning tool. The speaker starts from basic definitions, so it can be followed without prior planning experience.
What is an S-curve in project monitoring?
The speaker describes an S-curve as a graph that tracks project progress, with cost or manpower plotted cumulatively against time. In the worked example the planned curve rises by 1, 1 and 0.5 crore rupees over three months to 2.5 crore, while the actual curve reaches 2 crore. The gap between the two shows where work is lagging.
What does a planning engineer do, according to this workshop?
The speaker says the planning engineer prepares the construction work schedule, the inputs for the logistics plan, manpower histogram and milestone schedule, tracks drawing revisions, and monitors and updates progress against weekly or monthly plans. The planning engineer also keeps a critical issues dashboard, reports handover status and records project learnings.