Construction project planning: free, 75 minutes
One recording of about 75 minutes from a live civil engineering workshop in April 2023, narrated over slides. It covers construction projects and teams, planning versus scheduling, the five schedule levels, building a schedule with a WBS, critical path and baseline, then execution, reporting and software, and ends with audience questions.
24 chapters · published 6 Apr 2023 · 4,041 views as of 19 Nov 2026 · by Skill-Lync
Free. We ask for your name and phone once before it plays here · or watch on YouTube ↗
Who is this course for?
Civil engineering students and site engineers who want to understand how a construction schedule is built, tracked and reported before moving into a planning role.
What will you learn?
- State the PMI definition of a project and name the five phases of a project lifecycle
- Describe what the project management office, contracts and construction teams each do
- Explain the difference between planning and scheduling
- Tell the five levels of schedule apart and say who each level is written for
- Build a schedule in order: WBS, milestones, activities, links, then duration estimates
- Define critical path, float and baseline schedule as used in this workshop
What does each part of the course cover?
7 sections, in watching order. Click a timestamp to jump the player there. The video description has no chapter list, so these chapters and timestamps were written from the video itself.
- 0:0013 min · 5 chapters
Construction projects, lifecycle and the project team
The PMI definition of a project, the two broad construction domains of buildings and infrastructure, and the five phases of a project lifecycle, illustrated with a flyover contract. Then the project team in three parts: the project management office, contracts, and construction, with a delay penalty example.
- 12:353 min · 1 chapter
Project planning and how it differs from scheduling
Planning is described as determining the time frame and schedule for the project tasks, starting from an execution strategy for the flyover example, such as casting in situ or prefabricating. The speaker then separates planning, which covers many aspects, from scheduling, which covers time only.
Chapters
- 12:35Project planning, execution strategy, and how scheduling differs
- 15:497 min · 3 chapters
The five levels of schedule
Each level adds detail for a different audience, from a high-level milestone schedule for senior management to level 5 work for site engineers, foremen and subcontractors. The flyover is used first, then a residential development with substructure, footings, stub columns and concrete work broken down level by level.
- 22:4112 min · 3 chapters
Building a schedule: WBS, milestones, links and durations
The order of work: break the scope into a work breakdown structure, add zero-duration milestones, then activities such as staging, rebar, shuttering, concrete and curing for a pier. Activities are linked with finish-to-start and start-to-start relationships, and durations come from resource productivity, with a three-point estimate mentioned.
- 34:177 min · 3 chapters
Gantt chart, critical path, float and baseline schedule
Activities are drawn as bars on a Gantt chart in the Primavera screen. The critical path is defined as the path where a delay to any activity delays the project, with float of zero. A schedule becomes the baseline once the client or top management accepts it, and progress is measured against it.
- 41:417 min · 2 chapters
Execution, schedule control and reporting
Site teams send daily progress, the planning engineer updates the schedule, compares weekly or monthly progress with the baseline and issues revised or catch-up plans when work lags. Reporting runs from daily and weekly reports to the monthly progress report, including reasons for delay, with a question on rain.
- 48:4827 min · 7 chapters
Planning software and audience Q&A
Why Oracle Primavera is used for planning and monitoring in the speaker's view, then answers on a Primavera trial, practising it without a live project, how site engineers can move into planning, and a repeat of critical path and float. The close reviews a related programme.
Chapters
- 48:48Planning software and why Primavera is used
- 50:55Q&A: getting started in construction management
- 52:04Q&A: Primavera trial and cost (speaker's view in 2023)
- 54:21Q&A: learning Primavera without a live project
- 1:00:05Q&A: critical path and float on a 1000-activity project
- 1:00:59Q&A: moving from site or design roles to planning
- 1:10:25Closing: programme overview and certificate follow-up
Is the Construction Project Planning & Scheduling Technique course really free?
Yes. All 1 h 15 min of it is free on Skill-Lync's YouTube channel, with no payment. To watch it on this page with the chapter guide, leave your name and phone number once; you can also watch it directly on YouTube. It was published on 6 Apr 2023 and had 4,041 views as of 19 Nov 2026. This page adds the chapter guide, a study plan and what to learn next.
How long does the Construction Project Planning & Scheduling Technique course take to finish?
The video runs 1 h 15 min across 24 chapters. At one hour a day that is about 2 days; plan roughly twice that if you practise each exercise as you go. The longest section is "Planning software and audience Q&A" (27 min), so give it its own days.
Does the free Primavera P6 course come with a certificate?
The video description has a "claim your certificate" link, which now opens this page. To ask about a certificate for this course, leave your name and phone number in the form below and a Skill-Lync counsellor will call you back. The paid Skill-Lync courses linked here include a certificate along with mentor-reviewed projects.
What should I learn after this course?
The next step is Project Planning and Scheduling (free lessons), then Project Planning and Scheduling (₹40,000), then Post Graduate Program in Construction Project Management (₹2,75,000). The free course teaches the concepts; the paid Skill-Lync courses add graded projects, mentor feedback and, in the PG programs, placement support.
Which software does the workshop use for scheduling, and is it free?
The slides show schedules on the Oracle Primavera screen, and the speaker presents it as the main planning and monitoring tool. In this 2023 recording the speaker says a trial of about three months can be downloaded but that company licences are expensive. Check Oracle's current terms yourself.
What is the critical path and what does float mean?
In this workshop the critical path is the path on which a delay to any activity, even by one day, delays the project. Float is the time an activity can be delayed without delaying the project, and critical activities have zero float. The speaker adds that Primavera software gives the critical paths.
What is the difference between a baseline schedule and a revised plan?
The speaker says a schedule becomes the baseline once the client, or top management, accepts it, and progress is measured against it. During execution the planning engineer may prepare catch-up or revised plans when work falls behind, while the baseline stays the reference for checking where the project stands.