Construction project planning: free, 75 minutes

One recording of about 75 minutes from a live civil engineering workshop in April 2023, narrated over slides. It covers construction projects and teams, planning versus scheduling, the five schedule levels, building a schedule with a WBS, critical path and baseline, then execution, reporting and software, and ends with audience questions.

24 chapters · published 6 Apr 2023 · 4,041 views as of 19 Nov 2026 · by Skill-Lync

Free. We ask for your name and phone once before it plays here · or watch on YouTube ↗

Who is this course for?

Civil engineering students and site engineers who want to understand how a construction schedule is built, tracked and reported before moving into a planning role.

What will you learn?

  • State the PMI definition of a project and name the five phases of a project lifecycle
  • Describe what the project management office, contracts and construction teams each do
  • Explain the difference between planning and scheduling
  • Tell the five levels of schedule apart and say who each level is written for
  • Build a schedule in order: WBS, milestones, activities, links, then duration estimates
  • Define critical path, float and baseline schedule as used in this workshop

What does each part of the course cover?

7 sections, in watching order. Click a timestamp to jump the player there. The video description has no chapter list, so these chapters and timestamps were written from the video itself.

  1. 0:0013 min · 5 chapters

    Construction projects, lifecycle and the project team

    The PMI definition of a project, the two broad construction domains of buildings and infrastructure, and the five phases of a project lifecycle, illustrated with a flyover contract. Then the project team in three parts: the project management office, contracts, and construction, with a delay penalty example.

    Chapters
    • 0:00Welcome, speaker background and agenda
    • 3:25What a project is: the PMI definition
    • 4:53Construction projects: buildings and infrastructure
    • 7:11Project lifecycle: five phases, shown with a flyover contract
    • 9:07The project team: PMO, contracts and construction
  2. 12:353 min · 1 chapter

    Project planning and how it differs from scheduling

    Planning is described as determining the time frame and schedule for the project tasks, starting from an execution strategy for the flyover example, such as casting in situ or prefabricating. The speaker then separates planning, which covers many aspects, from scheduling, which covers time only.

    Chapters
    • 12:35Project planning, execution strategy, and how scheduling differs
  3. 15:497 min · 3 chapters

    The five levels of schedule

    Each level adds detail for a different audience, from a high-level milestone schedule for senior management to level 5 work for site engineers, foremen and subcontractors. The flyover is used first, then a residential development with substructure, footings, stub columns and concrete work broken down level by level.

    Chapters
    • 15:49Five levels of schedule and who each is for (levels 1 to 3)
    • 19:03Levels 4 and 5: construction managers, foremen and subcontractors
    • 20:01The five levels on a residential development example
  4. 22:4112 min · 3 chapters

    Building a schedule: WBS, milestones, links and durations

    The order of work: break the scope into a work breakdown structure, add zero-duration milestones, then activities such as staging, rebar, shuttering, concrete and curing for a pier. Activities are linked with finish-to-start and start-to-start relationships, and durations come from resource productivity, with a three-point estimate mentioned.

    Chapters
    • 22:41Building a schedule: WBS, milestones and activities
    • 28:01Linking activities: predecessors, successors, finish-to-start and start-to-start
    • 30:37Estimating activity durations from resource productivity
  5. 34:177 min · 3 chapters

    Gantt chart, critical path, float and baseline schedule

    Activities are drawn as bars on a Gantt chart in the Primavera screen. The critical path is defined as the path where a delay to any activity delays the project, with float of zero. A schedule becomes the baseline once the client or top management accepts it, and progress is measured against it.

    Chapters
    • 34:17Gantt chart: bars, planned dates and the Primavera screen
    • 36:33Critical path and float
    • 39:33Baseline schedule: why the client or management must accept it
  6. 41:417 min · 2 chapters

    Execution, schedule control and reporting

    Site teams send daily progress, the planning engineer updates the schedule, compares weekly or monthly progress with the baseline and issues revised or catch-up plans when work lags. Reporting runs from daily and weekly reports to the monthly progress report, including reasons for delay, with a question on rain.

    Chapters
    • 41:41Execution: daily progress, updating and controlling the schedule
    • 44:48Reporting: daily, weekly and monthly progress reports
  7. 48:4827 min · 7 chapters

    Planning software and audience Q&A

    Why Oracle Primavera is used for planning and monitoring in the speaker's view, then answers on a Primavera trial, practising it without a live project, how site engineers can move into planning, and a repeat of critical path and float. The close reviews a related programme.

    Chapters
    • 48:48Planning software and why Primavera is used
    • 50:55Q&A: getting started in construction management
    • 52:04Q&A: Primavera trial and cost (speaker's view in 2023)
    • 54:21Q&A: learning Primavera without a live project
    • 1:00:05Q&A: critical path and float on a 1000-activity project
    • 1:00:59Q&A: moving from site or design roles to planning
    • 1:10:25Closing: programme overview and certificate follow-up

Is the Construction Project Planning & Scheduling Technique course really free?

Yes. All 1 h 15 min of it is free on Skill-Lync's YouTube channel, with no payment. To watch it on this page with the chapter guide, leave your name and phone number once; you can also watch it directly on YouTube. It was published on 6 Apr 2023 and had 4,041 views as of 19 Nov 2026. This page adds the chapter guide, a study plan and what to learn next.

How long does the Construction Project Planning & Scheduling Technique course take to finish?

The video runs 1 h 15 min across 24 chapters. At one hour a day that is about 2 days; plan roughly twice that if you practise each exercise as you go. The longest section is "Planning software and audience Q&A" (27 min), so give it its own days.

Does the free Primavera P6 course come with a certificate?

The video description has a "claim your certificate" link, which now opens this page. To ask about a certificate for this course, leave your name and phone number in the form below and a Skill-Lync counsellor will call you back. The paid Skill-Lync courses linked here include a certificate along with mentor-reviewed projects.

What should I learn after this course?

The next step is Project Planning and Scheduling (free lessons), then Project Planning and Scheduling (₹40,000), then Post Graduate Program in Construction Project Management (₹2,75,000). The free course teaches the concepts; the paid Skill-Lync courses add graded projects, mentor feedback and, in the PG programs, placement support.

Which software does the workshop use for scheduling, and is it free?

The slides show schedules on the Oracle Primavera screen, and the speaker presents it as the main planning and monitoring tool. In this 2023 recording the speaker says a trial of about three months can be downloaded but that company licences are expensive. Check Oracle's current terms yourself.

What is the critical path and what does float mean?

In this workshop the critical path is the path on which a delay to any activity, even by one day, delays the project. Float is the time an activity can be delayed without delaying the project, and critical activities have zero float. The speaker adds that Primavera software gives the critical paths.

What is the difference between a baseline schedule and a revised plan?

The speaker says a schedule becomes the baseline once the client, or top management, accepts it, and progress is measured against it. During execution the planning engineer may prepare catch-up or revised plans when work falls behind, while the baseline stays the reference for checking where the project stands.

Last updated 19 Nov 2026 · Course length, chapters, views and dates from the YouTube video on 19 Nov 2026 · Grow by Skill-Lync: free lessons from every course

Finished the course?

Ask about the certificate or your next course.

Leave your name and phone number. A Skill-Lync counsellor calls you back within one working day about the certificate for Construction Project Planning & Scheduling Technique and the course that fits where you want to work.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Free full course · Skill-Lync

Start watching

Free, no payment. Leave your name and phone once and the whole Construction Project Planning & Scheduling Technique course plays here, with every free lesson on Grow. A Skill-Lync counsellor may call you about the certificate or your next course.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.