Contract Award, Work Order Clauses and Contract Closure

A free lesson from Skill-Lync's Contract and Subcontract Management course, on Grow by Skill-Lync · Last updated 16 Nov 2026 · Session: “Week 1 Session 3”

What will you learn in this free Contract and Subcontract Management lesson?

Covers contract award and closure under the Indian Contract Act 1872, using a sample work order. Reviews clauses such as defect liability period, variations with plus or minus 20 percent limits and insurance, then explains why proper closure avoids disputes.

  • Sample work order structure and scope of work
  • Defect liability period after completion
  • Variation clause with rates and the 20 percent limit
  • Why verified closure prevents claims and arbitration

What comes after lesson 3?

Later in Skill-Lync's Contract and Subcontract Management course (paid): lesson 4, Week 2 Session 1; lesson 5, Week 2 Session 2; lesson 6, Week 3 Session 1. The full course has 43 lessons (19 h 17 min of video); see the course overview or its price and syllabus.

Lesson transcript

Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.

Welcome to week 1 session 3. Students will be learning contract award and contract closure in this session. A contract is an agreement enforceable by law, the Indian Contract Act 1872. A contract is signed when an important or costly task is to be done. Let us say if you are joining a job, the employer will ask you to sign a contract. Now this is a very simple sample that I have tried to put in. This is a work order. So this sample will give you an overview how the actual contracts in the real business world looks like.

At the top you will put the date and on the right hand corner the work order it is written. Typically to whom you are issuing the name and details, the address will go in and then kind attention the person who is the authorized representative. Now here then you put the subject, what this particular work order is about. As you can see here it is states that cable laying and making infrastructure for aerial lighting in the reception building at our XXXX site near X. You write about the scope of the work then. So here in this case it includes the construction of temporary electrical infrastructure.

And you have to put as much details that you can put in. In the large contracts this scope of work part will go into 100 and 200 or 300 pages or even more giving every possible detail that you can put in. And what we have learned so far in the week 1 session 1 and 2 that makes you eligible for understanding that what are the scenarios that can arise during the project stage. All those things have to be written down explicitly and in a more most transparent fashion.

The price part is very important. The price part is very important. Here it is stated that the value of the item rate work contract. So it indicates that this particular contract is a item rate work contract. What is item rate work contract? In case of a item rate one rate contract actually the BOQ or the bill of quantities is mentioned. All the items that are executed that has to be mentioned. As for example here you can see a sample BOQ or bill of quantity where if you see the serial number in the first column there five items here actually this consist of total nine items.

So in it is itemized contract and you have to mention all the items very very clearly in the first serial number one I am reading out in the description of item is laying of 185 square mm by 3.54 AI armored cable 1.1 kV grade on ready trench bamboo poles labor only. So this makes it very clear that this item is labor only and no material part will be supplied by the contractor. Responsibility of the material automatically has to be with the owner. The unit the most important part the unit is also known as unit of measurement. How we will be measuring?

In short from sometime you will find it is written UOM. So that is meter in this case. Then the total quantity mentioned is 360. The rate which has been quoted and accepted by the contractor and accepted by the owner is 45 and hence 360 multiplied by 45 16200 in the extreme right hand side column. That is the amount. So this is the amount. So this is the amount. So this is the way a BOQ based or item rate contracts are written. All the items will come under the head description of item against that there will be a typical unit whatever is mutually agreed and accepted by the owner and the contractor.

And then there will be the quantity which is based out of quantity estimation then rate and then amount. I am reading the 5 serial number supply and installation of earthing station with 50 mm dia GI pipe medium gauge 3.64 mm trick 3 meter long excavation of art refilling with salt charcoal water pipe. Masonry inspection chamber with CI hinged cover at top etc. As required. The unit here is number 4 numbers has to be executed as per the contract and the rate mentioned is 4500. So 4500 multiplied by 4 18000. Similarly the other items are put in and at the bottom you see it's written the price is exclusive of taxes as applicable as per the statute and shall remain and for fixed till the execution of the order and the total what is the total amount that is coming at the bottom adding all the nine rows you get the total value of the contract minus the taxes as applicable. Then comes the condition of contract again later on we will be learning GCC, SCC which is general condition of contract and special condition of contract. These are the basic conditions of here basic of the contract put down for example 1A stage you shall work as per the guidelines mentioned in design drawings BOQ and instruction from our authorized representative.

In point number two contract period or completion schedule it is extremely important it's right here the contract says you will mobilize and comments work immediately and the work shall be completed as directed by your authorized engineer in charge within next three to four days subject to site condition. Then comes the terms of payments then retention and reconciliation electricity and water whether that will be here it is mentioned electricity and water for the purpose of the said work shall be supplied by us free of cost us meaning the owner. In many cases it happens that the contract will say that the contractor will have to arrange for electricity and water. So in this part as you develop such contract as you see the sample the understanding agreement between the two parties are the key and all this parameters this lines the statements and what you want to put in will depend on what owner is proposing and what contractor is agreeing. Point number six is about safety and statutory compliance sense point number seven clearance of site and eight is defect liability period. So defect liability period it says that the defect liability period is of six months from the date of issuance of the practical completion certificate meaning if there is anything wrong happening with the workmanship of the contractor contractor then the contractor is automatically liable to get this those problems rectified free of cost.

The variations variation is very important the here it states clearly that employer reserves the right to instruct the subcontractor to carry out variation work the payment for such variations will be evaluated using existing rates for works of a similar nature or using rates to be established for new works for which there are no prevailing rates on basis of reasonable costs plus 20 percent for overheads plus prevailing taxes were applicable. It is clearly understood that the quantities as contained under schedule of rates are approximate and subject to final measurement.

The rates as contained under SOR shall be valid and applicable for a variation up to plus or minus 20 percent in the contract sum and not on individual items. So understand this point very well what this clause says that all the items that their quantities may vary and it can vary up to any extent but the in totality the maximum variation allowed is either plus 20 percent or minus 20 percent. If it is going beyond that then this particular contract will not work on that extra work and you have to work out a extra item. Number 10 insurance so here what are the insurances for example workman's compensation insurance this particular sample contract talks about so what you need to do with insurance as a contractor those are mentioned here. Then point number 11 laws for 12 termination 13 is the reference reference means that the quotation of the contractor in case of a notice inviting tender in the reference you have to talk about all those notices and all the RFPs and submissions.

In this case this particular contract may be out of a single quote or at least the NIT process was not done saying that that is the reason that it is there the contract says that the reference this has a reference to your quotation so and so dot dated so and so. Now 14 finally the acceptance the order is forwarded to you in duplicate please return the duplicate copy duly endorsed and stamped as a token of your acceptance in the terms and conditions and then it is assigned by the authorized signatory.

Now we come to Award stands for the contract award meaning when all this quotation is evaluated and finally a contract is finalized and the owner is now handing over the order to the contractor that is known as contract award. It refers, bullet point number two, it refers to the process of formally notifying a tenderer that they have been selected as the supplier or vendor for the particular contract. Third bullet point, a tenderer is a person or company that estimates the cost of the proposed project and submits the offer or someone who presents a payment to another.

An example of a tenderer is a contractor who bids on painting of a house which the very simple example like you are having a plan to paint your own house, you asked for quotations and the contractors who with their experience and estimation submit you a quote are the tenderers. And the award, the second bullet point in this slide, say award is usually preceded by a LOI or a letter of intent. What actually happens in large contracts or large awards, there are a lot of documentation which even after mutually agreeing and accepting verbally, it takes some time to actually give the formal award.

So, usually the industry practice is to give a LOI or letter of intent saying that yes, you are the person whom we have selected and you can do start your planning if the LOI allows the contractor can work on their mobilization as well depending upon the statements of the LOI or what type of LOI it is. So, that LOI actually makes a formal intimation to the selected bidder which usually precedes the main work order or the main award in order to save a lot of planning time.

Nevertheless, LOI should not be confused with the award. It is only a pre-intimation to the award. We will learn about pre-award. What is the pre-award? That is the tender list, contract development, invitation, notice inviting, tender or NIT offered by the tenderers or bidders, tender clarification and response. In most of the large project, it happens whenever a participating bidder comes in, start understanding the project. They have a lot of technical queries and they put in all the queries to the owner. Owner needs to reply them and back and forth a lot of knowledge exchange happens.

Finally, in pre-award there is tender evaluation and then the award LOI I have already discussed in the previous slide and finally after the LOI, if things are absolutely in line with the discussions, then the purchase order and work order is released. Next, what you need to know in the post-award section is also very important. The post-award means the deliverables, it may be drawings, it may be certain local sanction commitments, it may be also due to some reason you need to exchange or give some special input to the contractor.

All this kind of deliverables will come in the post-award and the general administration obviously will come in and finally the closeout is that is the entire award process is completed. Now, in the session 3 of week 1, we will come to the final topic or I will say element and this has a lot of significance and this is the contract closure. First bullet point, it refers to the process of completing all tasks and terms that are mentioned as deliverables. For a contract to be ultimately and conclusively closed, the seller must have completed all components of his deliverables.

So, all the deliverables that are listed in the contract, so that has to be completed. So, it can be for a construction project, say the construction of a building project, not only the completion of the building, in all respects whatever is mentioned in the contract. For example, the as bill drawings, if that is listed in the deliverables, those deliverables will also have to come in in order to close the contract conclusively. As an example, if a contractor asks for supply of a CTM or cube testing machine at a particular site within a specified time frame, then the contract closure will ensue only when the said machine is supplied as per all the detailed specification mentioned in the contract and within the specified time frame as mentioned in the contract.

Bullet point number 2, improper and unverified contract closure often leads to claims and disputes and arbitration. We will know a lot about the claims, disputes, arbitration, which are the interesting and important sub-domains of contract and sub-contract management. But if a proper contract closure happens, usually the cases of claims, disputes and arbitration never arise. So, we have now completed our week 1 learning for our 12 week long course of contract and sub-contract management. We have in this week learnt about the important terminology and in contract management.

I request you to do more research on such terminologies, whatever related words you find, you can do it through internet search, you can ask your friends and seniors in the industry. Because my intention in the week 1 was to give you a base and I have already talked about some specific point about which I need you to do some research in the industry through internet or through live projects. That will help you to understand the next topics in our future classes very easily. Bullet point number 2 here, the scope we have learnt in depth and scope document you should remember is the key to a good prudent contract.

The clearer the scope document is, the better the quality of the contract is. And in order to prepare a proper scope document, it is essential to have the industry knowledge. And in many cases, when a tender manager is working on a scope document, it is common in the industry to take a peer review, to hire good project management consultants, good industry experts, so that the technical details and in-depth knowledge is shared in that scope document itself. You will also come across a term called project charter and they are not exactly the scope document and project charter are not exactly the same things, but they have similarities.

And I will also tell you to understand what project charter is. It basically says that how the projects are going to run. So, now, often when the boundaries of this contract management, project management are becoming blurred, I would also request you to do some research on the project charter as well. In this week, we have also learnt about what an organization is. We have learnt about awarding and closing a contract. And about the organization and award, contract award, I have given you the full details. So, now you can even talk about why the organization is important or the understanding of an organization for which you are working or preparing the contract is important.

And finally, the closing of contract, so I believe students, you have got a good insight about the subject of contract and subcontract management in our week one classes, which is divided into three sessions. And in the next class, I will be, that is the week two, I will be talking about the essential elements of contract and industry good practice. Thank you.

Want the rest of Contract and Subcontract Management?

Get the full course syllabus and fees.

The full course is paid (₹40,000). We'll send the syllabus and call you back within one working day.

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.

Full course · paid

Unlock the full Contract and Subcontract Management course

The remaining 40 lessons, mentor-reviewed projects and a certificate come with the paid course (₹40,000). Leave your details: we'll send the syllabus and fees and call you back.

Get the syllabus and fees

A counsellor calls you back within one working day.

By submitting you agree to our Terms and Privacy Policy.

Grow by Skill-Lync · free lesson

Start watching

Free, no payment. Leave your details once and every free lesson on Grow plays straight away. A Skill-Lync counsellor may call you about the full Contract and Subcontract Management course.

By submitting you agree to our Terms and Privacy Policy.

Talk to a career counsellor

Talk to a career counsellor

Free 20-minute call. We'll map the right course to where you want to work.

By submitting you agree to our Terms and Privacy Policy.