PMBOK Process Groups, Project Charter and Controlling a Construction Project
A free lesson from Skill-Lync's Construction Project Management Fundamentals course, on Grow by Skill-Lync · Last updated 16 Nov 2026 · Session: “Week 1 Session 3”
What will you learn in this free Construction Project Management Fundamentals lesson?
Walks through the PMBOK process groups defined by PMI: initiating, planning, executing, controlling and closing. Covers the feasibility study, what a project charter contains, contract administration, and controlling through performance reporting, quality, schedule and cost control.
- The five PMBOK process groups and their phases
- Project charter contents and who reads it
- Executing and contract administration
- Controlling: work verification, quality, cost and change management
What comes after lesson 3?
Later in Skill-Lync's Construction Project Management Fundamentals course (paid): lesson 4, Week 1 Session 4; lesson 5, Week 2 Session 1; lesson 6, Week 2 Session 2. The full course has 48 lessons (25 h 1 min of video); see the course overview or its price and syllabus.
Lesson transcript
Machine transcript of the lesson audio (lightly cleaned). Technical terms may contain errors; the video is the reference.
Hi, everyone. I welcome you to the part three of the C in this session. What are the different project earlier? These are defined by the PMBOK. We saw that it is a project management body of knowledge as developed by PMI, which is nothing but the project management institute. Looking at the names of this process groups, it will be easy to understand those are defining the phases. If you see it start with planning, executing, and the last one is about closing. Initiating, it is where the project is conceptualized.
Decision of understand the importance to be executed. The planning phase will arrive. Planning the activities for the project. What are the different types of plans which need to be going to discuss in this session today? Then executing, yes, it is actual performance of the project, execution of the project on the site. What are the different processes under execution? Those also will be learning today. Then comes management, different parts of controlling process groups. From the name itself, we can understand it is the last process group. What processes take place during the closing phase? We'll be discussing what are the different processes which happen in this phase of the project.
I believe it is very important, but at the same time, it is one of the most ignored processes upon how we define the project. It gives us the, I believe it is very much important to have better control on the initiating activities of initiating process group. If you see here, we have business case, identification, project charter document, and team formulation. We are going to discuss each and every activity of this or every document which is mentioned here in detail. In itself, we can understand the business case.
But the business case is, this is the requirement of the project. Why we need to have their long term vision. They have long term plans. So whenever business case document is created, alignment with long term plans. So once we say the long term plans, which are nothing but just to give example, let's say a company for hospitality, let's say commercial project. So that may not be on their long term plans, on the long term plans that they want to be a big hospitality company. So for them, the right aligned project will be maybe the hotel project.
Decisions may be taken whether the project is aligned with the company's long term vision or not, long term plans or not. Then there will be also taken a note for tangible benefit project. Tangible means measurable. There must be certain measurable benefits, which we should be able to recognize from the project. We have a long term goal for the company. We must know what exactly we are going to achieve in that plan. So whenever we have the project that also we need to see in the business case, how long it is going to be taken to execute the project.
This timeline may be very high level at very high level, but it needs to be there with certain milestones identified. This is about the possible resource commitments. Any project will require certain resources. And from the owner's perspective, it would be important to note how much funding is going to be required or any other resources which need to be put on the project for the completion. Who are the different stakeholders in an owner company who will be involved in project execution. So all these things need to be evaluated in the business case.
What are the possible risks for the project? This risk can be external. Those can be internal. Policy changes from the government also can be one of the risks. Those can be positive or negative risks. So all those things need to be considered whenever the business case is being prepared for the project. This happens in the sequence. These things may be prepared in parallel, but the feasibility study is very much important for the project. It is a document that establishes if it is worth undertaking the project.
So what exactly we are saying it here. We have a business case. We know that the project is required, but the benefits which it is generating, whether it is worthwhile. I believe there will be multiple options. This study is undertaken to check the possibility of each and every project, whether it is worth. It depends on the existing records and the possible projections. The existing records may be internal based on the company's history or a company's experience. It can be from the records of the industry which are available in the industry, outside industry, the company which is working for the past year.
So from that, as well as some possible projections, which are identified by the company or by the industry standards, which we are able to see. It considers different financial viability. So basically the feasibility study checks the viability of the project from different aspects, whether it is a technical aspects, methodology, whether we have the technical requirements to execute the project or not, or do we have the enough funds to support the project, to execute the project. So that also will be considered during the feasibility study. And once the project is executed, whether we have enough manpower for the operations or many of the times what happens that the initial cost of the project or during the execution, it is less.
But the operation which is going to be there for next 20, 40 years or even longer becomes a very heavy and it may not be viable to continue working on that project. Or I will say to continue the operations. So that viability also need to be taken care of along with any legal viability, whether is there any legal framework which may impose certain constraints executed will be taken care in the feasibility study. The feasibility study also identifies the underlying constraints, as I just mentioned, the legal constraints.
So there can be other constraints as well. So those need to be identified and properly recorded along with assumptions, if any, because all the decisions which will be taken will be based on this constraint and the assumptions. Assumptions may go wrong anyway, but those need to be properly recorded for the purpose of taking informed decision. So we just saw about the business case and we saw about the feasibility study. So the first thing which we actually discussed why we require the project. And the second thing we just discussed was whether it is viable to do the project, whether it is worth to do the project.
The next one, once actually the project passes through these two gates, the next thing comes about stakeholder identification. So just assume that project needs to be executed, it is identified. So the next important thing which needs to be done is about identifying the stakeholders. As you remember, we discussed this earlier, the stakeholders are any individuals or entity. I or I want to suggest that your객 doesn't include that active information and access information issues about how interesting things. So I just want to try and avoid that line, because while I talk that I find information that could ever change anything for myself, so that you probably appreciate that I'm pretty skilled at IT10 by Katie that, chat comes up in such a comment and I guess.
Those can impact the project in either a positive or negative way. So for the success of the project, stakeholders management is one of the aspects. So identification of stakeholders will be the key in that. The impact may be on the results of the project or the execution of the project. So what exactly that means? The stakeholders are having the impact on the project outcome or the actual execution. Just to give the example of it, the local residents who are having a certain interest in the dam project.
So initially it might have been decided that those will be displaced towards a village, which is let's say 25 kilometers far from the actual project site. But with the discussion with them, it may come up that they are not ready to go that far and we have to just relocate them to be maybe just 10 kilometers away from the dam site. So in such cases, the cost may increase. So if you just note this here, only the cost is increasing, but the end result, the end output or the product of the project remains same.
So that is the reason if you see here, the impact may be on the result of the project or the execution of the project. So whatever the example I just gave was about the execution of the project. But at the same time, if you just assume the metro project, where the people may request to change the alignment due to certain reason, so that you can consider as a result of the end product of the project itself. You are changing the original alignment itself. Okay, then moving on to the next point, stakeholders can be internal and or the external with different levels of influence and interest in the project.
As you remember, we discussed this particular concept, internal stakeholders and external stakeholders, but here important thing to note here is that there are different levels of influence and interest in the project. And based on the influences, they will be having the impact on the project as well, higher the influence, higher the impact, similarly, higher the interest, higher the impact. Okay, then we will see another point for the stakeholder identification. The last one, prepare the stakeholder communication document. Yes, at the start of the project, it would be very wise thing to do to identify the stakeholders as well as prepare the communication document.
So that document will list down who are the stakeholders, who are the influencer group with respect to their impact and their influence and who need to communicate what and when with whom. So all these questions will be answered by this communication document, which will really help the project team to manage the stakeholders over the period of time when the execution is in progress. Then moving on to the last point in initiating, which is the project charter document, a very important document, I will say at the start of the project.
It is a concise document that gives the details about the project. Okay, so what details it will provide, we will just go through this, but important word here is about concise. So basically, it is like a summary of the project, which will be very useful to understand the project in totality. And if you consider the senior management or the senior executives who do not have much time to go into the details of the scope of the project or to understand the project, they can always refer this particular document to get the high level information about the project.
So as I was just mentioning, it is the first document in the project that describes the scope, the high level scope, along with how we are going to achieve that scope. What is the plan to achieve that scope? So when I say the plan, it is not only the timeline, but it is about the sequencing as well. And the sequencing, okay, just to give a simple example for the construction of building, the sequencing maybe start with substructure, then move on to the superstructure, then do the MAP works and the finishes.
So this can be so simple. But if you consider certain complex projects like the chemical plants or the dam or I will say any fertilizer factory, the metro project itself, we need to have a specific plan about which activities need to be done first. So just to give you just to give example of substation project as well, where we need to take care when the transformer will be available and for that, which particular building need to be constructed first. So that in case of, I will say the chemical plant, we need to identify the main process buildings, which will be taking care of all the activities, which will be done during the actual operation of the project or the process.
So we need to identify those buildings and those need to be targeted to start early and finish early. You can have lower emphasis on the other buildings like administrative building so that the operations can start early and the revenue generation can start early. So that is the reason the high level plan to achieve the scope is also mentioned in this document. It also mentions at high level about the required resources. What are the different resources are required on this project along with possible timeline? This will be again at high level with certain milestones when we are going to achieve a particular event or particular milestone that will be mentioned in this document.
And this is a document where again, the constraints and the risk will be notified to the wider audiences. Because the earlier document, which we were discussing about the constraints and the risk, that is a feasibility study, it will have a smaller audience. It will be actually limited to a particular set of people. But the project channel document, which is available for the wider range of audiences, they will also know what are the constraints and risks involved in the project. And the way I was mentioning, it is very useful for understanding the project very quickly without going into the details.
The senior executives don't have much time to go into details. So they will just refer this project charter and they will get a fair idea about the project. So with this, we will just go into the details what this project charter will contain because that will give idea to students. So if you see it here, the first basic thing will be the general information about like project title, the brief project description, where it is, how it can be reached, what is the scope. So those information can be actually provided here.
Who has prepared this document? When it was updated last time? What is the latest revision? So these basic information about the documents will be also provided along with specific objectives of the projects. So what are the different benefits which will be achieved through completing the project? What are the possible problems to achieve this? What are the end results expected? And what are the deliverables? So how we actually differentiate between the results expected and the deliverables? So just to give the example of, let's say, hospital building, where the result expected may be to increase the ability to serve the patients in a particular rural area.
Okay. So that is the end result expected. We want to increase the capacity to treat the patients. But what is the deliverable? The deliverable for that may be, let's say, 100-bed hospital. So that is the measurable deliverable, which is helping to achieve the expected result. So along with the objectives, there will be assumptions also listed as we were mentioning it earlier. We will list and define all the assumptions, why those were considered. All assumptions should be validated to make sure that the project stays on the budget and schedule.
Okay. That will happen during the execution anyway. Then a project scope with a little more detail. Okay. Define the scope of the project. Also list the requirements that are excluded from the scope. This will be very much interesting, I believe. See, we actually provide the scope, what we want to do in the project, which we are going to do in the project. But at the same time, we are also listing what is, which is not part of the scope as well. But why it is important?
Because on a particular project, let's say only one small part is being done as a scope of work. Let's say it is a metro project and there are 10 different contractors working. And in the civil itself, there are two different contracts, one for viaduct, one for stations. But whose responsibility of the viaduct portion in station? Okay. What are the peers required in station? Area whose scope that work will be. So that is defined by any way by the contract. Station contractor will mention it as the station area peers or station area pillars are easier for the stakeholders to understand from this particular exclusions as well.
Important project milestones along with what are the deliverables at that particular milestone and definitely their dates. Those will be identified in the project charter. Then impact statement. What are the potential impacts? Which are the different systems which are going to be impacted if we are not achieving the milestone? So those also will be identified. This is very critical when multiple contractors are working on the same project. So we must know the relationships or the dependencies of the activities between different contractors. So the impact statement would have a critical, I will say it will have the importance there.
Then as I was just mentioning about the roles and responsibilities during the stakeholder discussion, this particular document will include who is the sponsor, that is nothing but the owner, basically who is funding the project. Then who is the project manager for the team, who is the project manager for the team, who are the team members with their roles, who are the customers, that is nothing but the end users, the sponsor and customer may be the same entity. And if there are any subject matter experts or the consultants involved. So all the stakeholders basically will be listed here in a project charter. So these are the roles where at the same time their responsibilities also can be listed out.
Apart from that, we will also have what are the resources which need to be committed for the project in terms of let's say funding or any personal to be provided for the project or the material which the owner has decided to be to be supplied to the contractor. So all these things can be mentioned here. It will also have certain risks listed, which are identified at the time of creating the project charter, because this is a continuous process, the register is continuously updated with identified risks.
So when we identify the risk at the same time, the mitigation strategy is also mentioned there. There can be multiple mitigation strategies like avoid the risk or transfer the risk or mitigate the risk through resolution. So there are different strategies. And for any project, there has to be a success measurement. There has to be a metric by which we will be able to know whether the project is successful or not. So those metrics also will be the part of project charter document. Then obviously in the last, there will be the signatures which you will be having from different stakeholders if required or it can be an internal document.
So based on the company policy, the different people will sign the document. Okay. In the initiating, there is one more part which we need to take care is about team formulation. Okay. So again, this will happen, let's say, parallelly with the project charter document. So here what we are doing in the team formulation is we are identifying the different roles. In fact, whatever the roles are identifying during the team formulation will be part of the project charter document. So the team formulation document will identify the different roles on the project and it will define their responsibilities.
So how we define it? Those are defined through a matrix called the RACI matrix. What exactly the meaning of RACI? The RACI is the short form for responsible, accountable, concerned and informed. So basically through RACI matrix, we are able to identify who are the stakeholders who are responsible to execute the work, who are accountable for the work, who need to be consulted before the work start and who need to be informed that the work is being carried out or it is done. So that is how we actually define the RACI matrix.
I will just give you the example of the same. So if you see it here, this is a matrix as the name suggests. On the left hand side, the first column is about the project task. We have tried to identify what are the different tasks during the different phases or between the process groups. And the columns, I am able to see all the roles which are there on the project. And we are identifying who is responsible for what and which activity each role need to be performing against a particular activity.
So we will take the example of let's say construction plan. If you see here, the construction plan, the planning engineer and execution engineer, they are responsible people. So why both those people? Because the planning engineer will create the baseline schedule. Okay, so he is the responsible person, he or she, they are the responsible people to do it. But the execution engineer will also prepare the production plan. Whenever at the site level, we need to have the look ahead program or we need to identify what are the activities to be done in the next one.
So such type of program need to be created by execution engineer. So they are the direct people who will be creating it. Those are responsible to execute this, but their respective bosses, those are accountable. Ultimately, the project manager is accountable for everything which is happening because all the team members are supporting to the project manager. So whatever the team members are doing, the project manager is accountable for their work. Even though something goes around, he may not be responsible for it, but he is definitely accountable for it.
While the construction plan is created, the planning engineer or the execution engineer, they cannot create it in isolation. They cannot actually be in a particular silo and create it. They need to consult the plan with different other people on the project like execution manager, the designer, to just take the input of how much time it is going to take for the design. Then the design head as well possibly. Then the safety executive, safety head. So these are the people who need to be consulted along with the quality people.
So the planning engineer will create the plan for the construction by consulting with this different profiles or different roles. So that is the reason if you see each one is identified as a to be consulted with basically. Okay. And the person from the head office, let's say VP operations, he need to be only just informed that the construction plan is being prepared or it is completed. So this type of RACI matrix is prepared and this is a very useful whenever there is a discrepancy or there is any, any, the issue which is happening at the site, who should do what?
They can always come and they can always refer this RACI matrix, which will be very useful for the people to understand their roles and the responsibility. Okay. With this, I would just like to move on the next part of the topic or the next part of the session, which is project process groups. Next part is about planning. We just completed only the initiating the first part planning. Another important process group, what it will contain. It will contain co-planning. Okay. The way we just discussed earlier, the planning, how I am going to perform a particular scope or how I am going to execute the project at high level.
That can be the scope planning. Activity planning, that is the detailing out those activities or the work packages. The scope is divided into different activities. Then the resource planning, each and every activity will require certain resources. So we need to plan those resources as well. Each resource will come with certain costs. So the cost planning also need to be done for the project along with procurement. So the procurement planning. So what exactly the procurement planning we need to do? What are the materials which will be required?
When those will be required? How I am going to perform a particular work package with that? I am going to do it myself or whether it will be done by the subcontractor. So those planning also need to be done along with risk response planning. We actually talked about risk, right? How we are going to mitigate the risk. We discussed that. So basically that planning for the identified risk also need to be done. I am not going to go into the details of each. I am not going to go into the details of each.
This is great. Thank you. Group activities, resource, cost, procurement, or risk response planning because during the different sessions, in fact, we have a separate planning session for time as well as cost. We are detailing out as a different session itself rather than doing it in a short term here. So let me go to the next part, which is executing the next process group. Executing, I'm sure it may not be difficult to understand because whatever we saw, whether it is initiating or happened behind the doors, not many of the people may understand what is happening, but execution, you will be able to see it happening on the ground.
Okay, the execution is the first part of executing process group. But what are the other things? It is the quality assurance. Quality assurance means defining the becomes a part of quality assurance. Then the next one is information sharing. You will definitely agree with our previous discussions regarding stakeholder management that information sharing is very critical between the different stakeholders. We also, we are going to discuss in detail. The last part of executing is about contract administration. So contract is signed off. Now we need to take care of the administration of it means fulfilling the requirements of the contract.
We have to fulfill the obligations, which are the part of the contract. So that is called as a contract administration. We have a separate station on the contract. The next process group we will be talking is about controlling. Controlling, very interesting process group, I believe, because it is the one where the actual work which is being done on the project is verified. Okay. I guess there are very few projects in the world which are done as per the plan for the schedule as well as the plan of the cost.
So the controlling is very much important. We need to check whether the project is going as it was planned or it is deviating from its path. And if it is deviating, how we can bring it back on the track. So that's what would happen in the controlling phase. As I just mentioned about the work verification will happen. The performance reporting will happen in this phase and the quality control. Okay. We defined the quality standards, but those need to be checked whether those are being followed or not.
So the quality control will happen during this phase along with schedule control, cost control and the most important thing about change management. Because basically any change to the scope will trigger the other changes as well like cost change or the schedule change or possibly the quality change as well. So we need to avoid the scope creep and try to limit the scope as it was decided at the start of the project. But based on the type of contract, the scope may change and we need to have a proper change management implemented so that we will be able to control the project in a better way.
Let's move on to the last process group, which is closing. Very easy to understand because we know this means that we are completing the project, but there are two types of projects. One is contract closeout, which means we are completing the overall scope of work, which we are executing. We are fulfilling all the obligations under the contract. But at the same time, there is an admin closure as well. You know, the project, when it starts, the contractor starts executing, he does a lot of mobilization activity.
He needs to set up a temporary office. He needs to set up temporary labor camp. There are other temporary facilities as well. A lot of people or the manpower is moving in the location of the project. So, those also need to be demobilized. So, that is called as a project admin closure. These things will happen during the closing phase. Thank you.